The dam

The water reservoir is filled with first tributary for 25 hours second tributary for 35 hours. Some time were both inlets open, then a second tributary closed and the tank was filled in four hours. What time water flowed from both tributaries? (Expressed in hours and minutes)

Result

t = 12:55 hh:mm Wrong answer

Solution:


1/25 t + 1/35 (t+4) = 1

12t = 155

t = 155/12 ≈ 12.916667

Calculated by our simple equation calculator.








Leave us a comment of example and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




Do you have a linear equation or system of equations and looking for its solution? Or do you have quadratic equation? Tip: Our volume units converter will help you with converion of volume units. Looking for a statistical calculator? Looking for help with calculating harmonic mean?

Next similar examples:

  1. 4 pipes
    roury The tank flows out by 4 pipes in 6 hours 120 hl water. How much water flows out of 5 pipes of the same diameter in 14 hours?
  2. Pumping
    pumps_1 The tank is filled with a larger pump in 12 hours and with scond pump in 15 hours. For how long does the tank fill when both pumps are switched on at the same time?
  3. Two looms
    stav On two different looms with different performance can be make required quantity of textile in 6 hours when both work together. On the first machine this quantity of the textile can make in 10 hours. How long should take make same quantity of textile on a s
  4. Two tributaries
    bazen_2 Two tributaries of the pool fill it in 10 hours. One of the tributaries would fill 15 hours. How long would fill the first tributary?
  5. Two pumps
    nadrz_4 The first pump fills the tank in 24 hours second pump in another 40 hours. For how long will take fill the tank if operate both pumps at the same time?
  6. 12 Moons
    12_mesicku Good Marry came to ask twelve moons for help with collecting strawberries. All twelve moons 1200 strawberries picked in 20 minutes. But lazy months July and August cease tear after 5 minutes. How many minutes in total will take collect strawberries?
  7. Candy
    friends Peter had a sachet of candy. He wanted to share with his friends. If he gave them 30 candies, he would have 62 candies. If he gave them 40 candies, he would miss 8 candies. How many friends did Peter have?
  8. Novak
    novakovci Novak needed to dig up three of the same pit in the garden. The first pit dug father alone for 15 hours. His second dig son helped him and it did that in six hours. The third pit dug son himself. How long it took him?
  9. Workers
    workers Two workers fulfill a certain task when working together for 8 days, the first if he worked himself done work in 15 days. How many days will do whole job a second worker?
  10. Collection
    maliny_1 John has collected half a bucket of raspberries in 45 minutes, Eva collects the whole bucket in an hour. How many minutes it would take to fill a bucket if the two children work together?
  11. Workers 2
    delnik Worker dug the trench for 7 hours, another worker for 10 hours. They recruited to work even one worker more. Digging should be done for 2 hours. For how long would dig third worker alone?
  12. Apprentice
    ucen Worker and apprentice execute the work for 6 hours. Worker performs himself in 10 hours. How long do the work of an apprentice?
  13. Working together
    malovka_1 One painter paint the nursery in 10 days, the second in 8 days. How many days will the nursery be painted if they work together?
  14. Tonic
    krem One package tonic consume Mom 12 weeks and daughter for 14 weeks. 4 weeks they use the same cream together and then only daughter. How many weeks endured tonic to daughter then?
  15. Dwarfs
    trpaslik Four dwarfs would prepare firewood for Snow White in580 minutes. After an hour and a half they recruit friends so that finished preparing the wood for 280 minutes. How many dwarfs they recruited?
  16. Digging companies
    companies Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days and the company D for 24 days. Work began together companies C and D, but after three days joined them other two companies. How long took to dig a pit?
  17. Equation
    rovnice_3 Solve the equation: 1/2-2/8 = 1/10; Write the result as a decimal number.