Twenty-seven 3476
Twenty-seven workers did the work in 12 days. In how many days would nine workers do the same job?
Correct answer:
Tips for related online calculators
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Workers 3291
The broad workers will do the job in 22.5 days. How many workers still need to be hired to do the job seven days earlier? - Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job? - Workers 54253
Four workers packed the goods with the same output in 6 hours. In how many hours would five workers do the same job? Express it in hours and minutes. - Two workers
Two workers will do certain work for 12 days. After eight days of working, one was removed, and the other finished the job alone in 10 days. For how many days would you do this work alone for each worker?
- Workers 82802
Five workers do a job in 20 hours. How long will it take two workers to do the same job? - Two workers
One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the company recalled the second, and the first completed the job in 5 hours. How many hours did they work together, and how much di - Three men
If three men can do a job in 8 days, how many men can do the same job in 6 days? - Together 39671
Three workers were to lay the parquet floor. If everyone worked alone, the first would finish the job in 30 hours, the second in 24 hours, and the third in 20 hours. How long will they do the floor if they work together? - Planting 27201
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f
- Apprentices 30051
Four apprentices worked on a glove order for 20 days. How long would it take for eight apprentices to complete the contract in the same job? - Together 5663
Two workers would do the work together in 2 days. The first would do some work here in 6 days. In how many days would the second worker do this work? - Three workers
Three workers got paid for work. First earn € 50, the second € 100 and the third € 60. For further work, we should receive € 735 together. How do you divide that amount to be distributed in the same proportion as the first job? - Forestry workers
56 laborers have employed planted trees in the forest. For 8 hour work, a day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day? - Reconstructing 23991
Three groups take turns reconstructing one piece of highway. The first group would finish the job themselves in 40 working days. The second group is in 24 working days, and the third group is in 30 working days. How many days do you do it together?
- The orchard
Four temporary workers harvested the orchard in 9 days. How many temporary workers do we need for six days? - Construction 7709
Two construction companies are working on the landscaping. The first would do the whole job in 12 days, the second in 20 days. How long will they work together if the first start working when the second has already worked 4 days? - Six workers
Six workers earned a total of CZK 12,600 per week on the construction site (5 working days). How much do seven workers earn in 10 days with the same daily average salary?