Minute average

In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 mins per box, Worker B takes 6 minutes per box, C takes 10 mins per box, D takes 15 mins per box. Find the average minutes taken per box by the group of workers.

Result

b =  1.714 min

Solution:

Solution in text b =







Leave us a comment of example and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




To solve this example are needed these knowledge from mathematics:

Looking for a statistical calculator? Looking for help with calculating harmonic mean?

Next similar examples:

  1. Invitations
    envelope For every 5 minutes writes Dana 10 invitations, while Anna 14 invitations. How long will write together 120 invitations?
  2. Workers
    okno2_1 Group of workers washing half of the windows of the building in two hours. How long will take half the workers wash all the windows of the building?
  3. Apprentice
    ucen Worker and apprentice execute the work for 6 hours. Worker performs himself in 10 hours. How long do the work of an apprentice?
  4. Performance
    workers_42 Two masons with the same performance would have made of plaster for 6 days. One of them, however, has increased its daily performance by 50%. How long would take they now to make plaster together?
  5. Painters
    painters The first team of painters would paint bridge in 15 days, the second in 10 days. After 3 days of working together second team goes out and continue only first team. How many days took second team to finish painting the bridge?
  6. Two valves
    pool_2 Water fill the pool by two valves for 11 days. After 7 days the first valve was stopped and the second valve fill pool for 7 days. How many days took to fill the pool each of the valves individually?
  7. Painter Pavel
    pixla_s_farbou Painter Pavel painted the fence for 16 hours and painter Petr the same fence painted for 13 h. How long should take painted the fence together?
  8. Fire tank
    fireman Whole fire tank was discharged once in 5 days by first out by second in $n days. Once firefighters pumped out 6/13 of water out from the tank and then let the water flow out both drain. How long take empty the tank?
  9. Bricklayers
    delnik_4 When a bricklayer works himself to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make 3 such houses together?
  10. Turners
    workers_25 Two turners perform joint work in 3 hours. The first turner would perform the job himself in 7 hours. How long would the same job last for a second turner if he worked alone?
  11. Two diggers
    two-diggers There are two diggers. One digger digs a pit 46 hours second gidding 2 times faster. a) how long took to dig a pit second digger b) how long took dig together
  12. Painters
    painter First painter painted fence himself for 9 hours, the second painter 1.6 hours sooner than first, and the third painters slowest up to 20 hours. How long took them paint fence if worked together?
  13. 5 pumps
    pump Five pump to pump 3 hours 1600 hl of water. How long pumped same amount of water 4 pumps?
  14. Digging companies
    companies Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days and the company D for 24 days. Work began together companies C and D, but after three days joined them other two companies. How long took to dig a pit?
  15. The tank
    pipe2_4 The tank had 9 inflows to be filled in 21 days. After 9 days, 3 trips out. How many days did the remaining 6 tributaries fill the tank?
  16. 4 pipes
    roury The tank flows out by 4 pipes in 6 hours 120 hl water. How much water flows out of 5 pipes of the same diameter in 14 hours?
  17. Theorem prove
    thales_1 We want to prove the sentense: If the natural number n is divisible by six, then n is divisible by three. From what assumption we started?