Minute average
In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 minutes per box, Worker B takes 6 minutes per box, C takes 10 minutes per box, and D takes 15 minutes per box. Find the average minutes taken per box by the group of workers.
Correct answer:
Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Do you want to convert time units like minutes to seconds?
Looking for a statistical calculator?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Weighted harmonic average
Ten workers will do some work in 2 minutes, five in 10 minutes, and three in 6 minutes. How many minutes per average worker per worker? - An insurance
An insurance company receives, on average, two claims per week from a particular factory. Assuming that a Poisson distribution can model the number of claims, find the probability it receives. three claims in a given week, more than four claims in a given - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - A truck 4
A truck covers a particular distance in 3 hours with a speed of 60 miles per hour. If the speed is increased by 30 miles per hour, find the time taken by the truck to cover the same distance in hours. - A ferry
A ferry with a capacity of 10 people takes a group of 13 men and 7 women across a river. Find the number of ways in which the group may be taken across the if all women go on the first group. - Production 24021
The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete - Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work. - Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together? - Books
The store received 100 copies of the new book. They were packed in 8 boxes, and the four books were separate. How many were in one box? - Complete 5584
The two workers dug together for 6 hours. The first worker would do the work himself in 14 hours. How long would it take for the second worker to complete the task? - Summaries
A specialist teacher observes the time taken by each of the students with learning disabilities to complete a psychological task. She summaries the times using the following: Time Taken(mins) ; 1-5; 6-10; 11-12; 16-20 No. of Student ; 2 ; 4 ; 12; 4 Using - Two workers
The first worker would complete the work in 8 hours, the other in 6 hours. After two hours of joint work, the worker left the first worker to a doctor, and the others completed the work themselves. How many hours worked did the other worker himself? - Improvements 70344
Two workers work equally efficiently and together can complete a given task in 5 hours. One worker improved his machine, changed his workflow, and increased his output by 40%. How long will it take both workers to complete the given task? - A person
A person buys 10 kg of commodity A at a rate of 2 kg per dollar, 20 kg of commodity b at a rate of 5 kilograms per dollar, and 30 kg of commodity C at a rate of 10 kg per dollar. Find the average price of kg per dollar. - The factory
The factory z can complete an order in 12 days, factory p in 18 days. How many days does an order completed when the first two days work only the factory z and then both factories? - Two painters
Two painters are assigned to finish painting the houses in a housing project. John can finish a house in 4 days. Kurt painted it in 3 days. How long would it have taken if John and Kurt worked painting the house together? - 15-kilogram 66524
The lift has a load capacity of 250 kg. How many 15-kilogram boxes can be taken by a person weighing 80 kg maximally?