Summer tires

Three tire servants have to change the summer tires on 6 cars in 2 hours. Mark's replacement would take 4.5 hours, Jirka would do it in 3 hours and 10 minutes, and Honza in 4 hours. Will they be able to replace all tires at the desired time?

Result

t =  1.269 h

Solution:

Solution in text t =







Leave us a comment of example and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




Looking for help with calculating harmonic mean? Looking for a statistical calculator?

Next similar examples:

  1. Three painters
    workers_37 The three painters have painted bridge. The first would work done in 5 days, the second in 6 days, and the third in 7.5 days. How long will the bridge work if they work together?
  2. Soldier
    digging_1 An experienced soldier digs a good trench in 30 hours. Two soldiers dug the same trench each 40 hours. How many hours will the ditch dig all three together?
  3. Holidays - on pool
    pool_4 Children's tickets to the swimming pool stands x € for an adult is € 2 more expensive. There was m children in the swimming pool and adults three times less. How many euros make treasurer for pool entry?
  4. Evening shift
    workers_43 While working the evening shift, Officer K took 8 hours to complete a task at his work station and Officer M took 10 hours to complete the same task at his work station. How many hours would it take Officer K and Officer M to complete the same task working
  5. Turners
    workers_25 Two turners perform joint work in 3 hours. The first turner would perform the job himself in 7 hours. How long would the same job last for a second turner if he worked alone?
  6. Two diggers
    two-diggers There are two diggers. One digger digs a pit 46 hours second gidding 2 times faster. a) how long took to dig a pit second digger b) how long took dig together
  7. Together 3
    painter_8 If Sally can paint a house in 4 hours, and John can paint the same house in 6 hours, how long will it take for both of them to paint the house together?
  8. Painters
    painter First painter painted fence himself for 12 hours, the second painter 3 hours sooner than first, and the third painters slowest up to 21 hours. How long took them paint fence if worked together?
  9. Pumping
    pumps_1 The tank is filled with a larger pump in 12 hours and with scond pump in 15 hours. For how long does the tank fill when both pumps are switched on at the same time?
  10. Apprentice
    ucen Worker and apprentice execute the work for 6 hours. Worker performs himself in 10 hours. How long do the work of an apprentice?
  11. Bricklayers
    delnik_4 When a bricklayer works himself to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make 3 such houses together?
  12. Painters
    natieraci Five painters painting the fence for eight days. How many days over will take work if paint the fence only four decorators?
  13. Minute average
    workers_40 In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 mins per box, Worker B takes 6 minutes per box, C takes 10 mins per box, D takes 15 mins per box. Find the average.
  14. Working together
    workers_49 One worker performs work in 3 days, the second in 5 days. How much do they work together?
  15. Fire tank
    fireman Whole fire tank was discharged once in 5 days by first out by second in $n days. Once firefighters pumped out 6/13 of water out from the tank and then let the water flow out both drain. How long take empty the tank?
  16. Painters 4
    painter_3 One painter will do the job for 12 days. After a 4 1/3 day he comes second to help him and complete work together for 8 days. How long would work the second painter himself?
  17. Workers 9
    okno2_2 If two workers fix two windows in an hour how many windows can 18 workers fix in the same two windows?