Two workers fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days.

How many days will do whole job a second worker?

Result

x =  8.1

Solution:

Solution in text x =







Leave us a comment of example and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




To solve this example are needed these knowledge from mathematics:

Do you have a linear equation or system of equations and looking for its solution? Or do you have quadratic equation? Looking for a statistical calculator? Looking for help with calculating harmonic mean?

Next similar examples:

  1. Workers
    two_workers Workers A and B will done work together for 15 days. They worked together 13.5 days. Then A worker became ill and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  2. Road repair
    workers_1 Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  3. Forestry workers
    forestry_workers In the forest is employed 43 laborers planting trees in nurseries. For 6 hour work day would end job in 35 days. After 11 days, 8 laborers go forth? How many days is needed to complete planting trees in nurseries by others, if they will work 10 hours a da
  4. Greenhouses
    sklenik Two workers would make installation of greenhouses for 54 hours. For how many hours does the installation 9 workers?
  5. Minute average
    workers_40 In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 mins per box, Worker B takes 6 minutes per box, C takes 10 mins per box, D takes 15 mins per box. Find the average.
  6. Bricklayers
    delnik_4 When a bricklayer works himself to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make 3 such houses together?
  7. 40% volume
    workers_41 40% volume with 104 uph (units per labor hour) 8 people working. What is the volume?
  8. Logic
    blue-barrel A man drinks a barrel of water for 32 days, woman for 54 days, for how many days they drink barrel together?
  9. Performance
    workers_42 Two masons with the same performance would have made of plaster for 6 days. One of them, however, has increased its daily performance by 50%. How long would take they now to make plaster together?
  10. Garden
    garden_2 Father dig up the garden in 9 hours. Son in 13 hours. How many hours take dig up the garden together?
  11. Excavation
    vykop_ryha Mr. Billy calculated that excavation for a water connection dig for 12 days. His friend would take 10 days. Billy worked 3 days alone. Then his friend came to help and started on the other end. On what day since the beginning of excavation they met?
  12. 3 cats
    mouse_1 3 cats eat 3 mice in 3 days. How many mice will eat 10 cats in 10 days?
  13. The tank
    pipe2_4 The tank had 9 inflows to be filled in 21 days. After 9 days, 3 trips out. How many days did the remaining 6 tributaries fill the tank?
  14. Pool
    pool If water flows into the pool by two inlets, fill the whole for 18 hours. First inlet filled pool 10 hour longer than second. How long pool is filled with two inlets separately?
  15. Tractors
    tractors Fields go plow two tractors with various performance. The first tractor plow whole field in 20 hours, the second tractor plow whole field 30 hours déle. How long take plow whole field with two tractors?
  16. 2 pipes
    time_12 2 pipes can fill a tank in 35 minutes. The larger pipe alone can fill the tank in 24 minutes less time than the smaller pipe. How long does each pipie take to fill the tank alone?
  17. Pipes
    water_pipe Water pipe has a cross-section 1405 cm2. An hour has passed 756 m3 of water. How much water flows through the pipe with cross-section 300 cm2 per 15 hours if water flow same speed?