Excavation

Mr. Billy calculated that excavation for a water connection dig for 12 days. His friend would take 10 days. Billy worked 3 days alone. Then his friend came to help and started on the other end.

On what day since the beginning of excavation they met?

Result

n =  8

Solution:

Solution in text n =

3 / 12 +(n-3)/12 + (n-3)/10 = 1

11n = 78

n = 7811 ≈ 7.090909

Calculated by our simple equation calculator.







Leave us a comment of this math problem and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




Do you have a linear equation or system of equations and looking for its solution? Or do you have quadratic equation?

Next similar math problems:

  1. Engineer Kažimír
    demagog_smer_1 The difference between politicians-demagogues and reasonable person with at least primary education beautifully illustrated by the TV show example. "Engineer" Kažimír says that during their tenure there was a large decline in the price of natural gas, pri
  2. Pool
    pool If water flows into the pool by two inlets, fill the whole for 8 hours. The first inlet filled pool 6 hour longer than second. How long pool take to fill with two inlets separately?
  3. Pipes
    water_pipe Water pipe has a cross-section 1087 cm2. An hour has passed 960 m3 of water. How much water flows through the pipe with cross-section 300 cm2 per 9 hours if water flow same speed?
  4. ŽSR
    luzianky Calculate fixed annual personnel costs of operating monorail line 118 km long if every 5 km is station, which serve three people - one dispatcher and two switchman in 4-shift operation. Consider the average salary of the employee 885 €.
  5. Tare
    camion Gross weight of shipment is 5188 kg and its tare is 5.6%. Calculate the net weight of the shipment.
  6. Forestry workers
    forestry_workers In the forest is employed 56 laborers planting trees in nurseries. For 8 hour work day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others, if they will work 10 hours a d
  7. Chickens
    chickens 2 chickens give 2 eggs in 2 days. How many eggs can give 8 chickens for 8 days?
  8. Cats
    cats Two cats caught two mice in two days. How many mouses will catch 6 cats for 6 days?
  9. Road repair
    workers_1 Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  10. Pizza
    pizza Five friends were together for pizza. Adam divided his pizza into thirds, Boris in quarters, Denis in patina and Luke in sixth. Then Simon also came to them. Each of the five boys gave him one piece, leaving him one whole pizza. In how many equal parts did
  11. Car
    american-cars Car goes from point A to point B at speed 86 km/h and back 53 km/h. If they goes there and back at speed 67 km/h trip would take 10 minutes shorter. What is distance between points A and B?
  12. Chocolate
    cokolada Leslie bought 8 same chocolates for 16 Eur. How many euros will he pay for 25 chocolates?
  13. Medicament
    tablets Same type of medicament produces a number of manufacturers in a variety of packages with different content of active substance. Pack 1: includes 60 pills of 600 mg of active substance per pack cost 9 Eur. Pack 2: includes 150 pills of 500 mg of active sub
  14. Washer
    pracka Washing machine drum wash at 58 RPM. Washing machine motor pulley has diameter 9 cm. What must be the diameter of the drum machine pulley when the motor is at 438 RPM?
  15. Tractors
    tractors Fields go plow two tractors with various performance. The first tractor plow whole field in 11 hours, the second tractor plow whole field 19 hours longer. How long take plow whole field with two tractors?
  16. Cyclist
    1cyclist Cyclist goes uphill 10 km for 50 minutes and downhill minutes for 29 minutes, both applied to the pedals same force. How long he pass 10 km by plane?
  17. Wage
    socik Increasing the minimum wage while maintaining the other parameters of the system, unemployment will be: