The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days?
Correct answer:
Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Production 24021
The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Workers
Ten workers must pave road street for 22 working days. After four days were for speeding up work, added two more workers. a) After how many work days now workers complete the paved road? b) How many working days does a total paved road take? - Apprentices 30051
Four apprentices worked on a glove order for 20 days. How long would it take for eight apprentices to complete the contract in the same job? - Completed 64134
Six workers will do the work in 8 hours. How many workers must be added if the work is to be completed in 3 hours? - Revitalization 39191
Workers are building a new sidewalk while revitalizing the housing estate. Six workers will do the work in 12 days, but this is a problem because the sidewalk must be completed in 10 days to complete the work on time. How many workers must be hired to com - Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Three workers
Three workers, A, B, and C, have to work on a specific task. Workers A and B completed the task in 12 days, B with C for 19 days, and A with C for 24 days. How long would it take to complete the task for everyone alone? How long would it take to complete - Two workers
The first worker would complete the work in 8 hours, the other in 6 hours. After two hours of joint work, the worker left the first worker to a doctor, and the others completed the work themselves. How many hours worked did the other worker himself? - The factory
The factory z can complete an order in 12 days, factory p in 18 days. How many days does an order completed when the first two days work only the factory z and then both factories? - Minute average
In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 minutes per box, Worker B takes 6 minutes per box, C takes 10 minutes per box, and D takes 15 minutes per box. Fin - Adjusting 72554
Two working groups are adjusting the park. The first group would do the work in 15 days, and the second in 25 days. How many days will they do the work together? - Mason with assistant
Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together they completed the work in the next three and a half days. How many days would he need an assistant for the same work? - Panel house
The construction company has two groups of workers. Group A has more members than B. Panel house was insulated by group A for ten days. They insulated the same block of flats together in 6 days. How many days would group B block insulate? - Installed 5793
A group of fitters installed the cable line in 9 changes, and the second group completed the same task in 1/3 less time. How many shifts would the third group do the same work if, with all three groups working together, the assembly took 2 shifts?