The work

The work was to be done by 150 workers. At the beginning of their work, The company reduced their number by 40, which increased the work time by 5 and 1/3 of the schedule. How long did work take?

Correct answer:

t =  20 d

Step-by-step explanation:

n=150 T=531=5+31=35 3+1=315+1=3165.3333  n(tT)=(n40) t 150(t5.3333333333333)=(15040) t  150 (t5.3333333333333)=(15040) t  40t=800  t=40800=20  t=20=20 d



Did you find an error or inaccuracy? Feel free to write us. Thank you!







Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions: