Railway repair extension
The railway company planned the repair of the railway tracks for 15 days. Only some employees showed up for work due to the coronavirus, and they extended the repair to 24 days. By what percentage did the repair time increase?
Final Answer:

Tips for related online calculators
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Our percentage calculator will help you quickly and easily solve a variety of common percentage-related problems.
Do you want to convert time units like minutes to seconds?
Our percentage calculator will help you quickly and easily solve a variety of common percentage-related problems.
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
basic operations and conceptsnumbersUnits of physical quantitiesGrade of the word problem
Related math problems and questions:
- Mass layoffs
The company's new management has announced that mass layoffs will be necessary due to the poor financial situation. It is estimated that the work that 5 employees did will have to be done by 3 employees. What percentage of the company's employees would lo - Highway repair
The highway repair was planned for 15 days. However, it was reduced by 30%. How many days did the repair of the highway last? - Six workers
Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate? - Production Increase Percentage
The company's monthly production increased from 352 products to 528 products. So, by what percentage did the original monthly production increase? - Production increase percentage
The company produced 300 vehicles a day. What percentage did production increase when they made 1,560 vehicles in 5 days? - City plan
The city planned to repair the highway section for 20 hours. Workers reduced this time by 20%. How long did the repair take? (express in hours and minutes) - Road repair time
Ten workers managed to repair the road in 22 days. After four days, two more workers joined to speed up the work. How many days does it take to repair the road?