Fulfilled 29001
Race A can fulfill the order in 12 days, and race B the same order in 18 days. How many days will the order be fulfilled if both plants work together?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Two companies
Company A can fulfill the order in 12 days, and company B the same order in 18 days. How many days will the order be fulfilled if only company A works on it for the first two days, then the remaining days for both companies? - Independently 12921
Factory A can fulfill the order independently in 10 days. Factory B fulfills the same order in 16 days. How many days will the order be completed if only plant B works on it for 3 days and then both plants together? - Modifications 3317
Workshop A can fulfill a specific order in 8 changes, workshop B in 10 modifications. How many shifts will the job be completed if workshop A works on only the first two shifts and both workshops work on the remaining shifts? - Seamstresses 4635
Eight seamstresses have to complete the order in 16 days. After four days, the two seamstresses switched to another job. In how many days will the order be fulfilled?
- Engineering 54971
Two engineering companies have the same production program. The first company would fulfill their orders in 20 days. The second company in 16 days. How long will the companies fulfill the order if the first company starts working 2 days earlier? - The factory
The factory z can complete an order in 12 days, factory p in 18 days. How many days does an order completed when the first two days work only the factory z and then both factories? - Fulfillment 5210
This company can complete the order in 168 days. The second company is better equipped and can fulfill the order in 120 days. The companies will fulfill the orders together. Determine how long it will take them to fulfill the order and in what proportion - Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job? - Seamstresses 82403
Eight seamstresses sew an order in 85 hours. After 21 hours, 3 seamstresses had to leave for other work. In how many more hours will the order be fulfilled? How many hours did the whole job take?
- Working together
Zeru can complete a certain job in 5 days, and Tulu can complete the same job in 3 days. How long will they complete the job if they work together? - Together 3
If Sally can paint a house in 4 hours, and John can paint the same house in 6 hours, how long will it take for both of them to paint the house together? - Insulation
Two workers insulate the house for five days. After the first day of working together, only one worker continue to cover the house. How many days will the house be insulated if every worker has the same work tempo? - Situation 78694
There is a geyser and a volcano in a nature reserve in Iceland. The geyser erupts regularly every 18 days, and clouds of smoke rise from the volcano every 40 days. how many times in the course of 9000 days will there be a situation where we can observe bo - Together 28411
Worker A will dig a trench in 12 days. Worker B will dig a trench in 18 days. How many days will it take them together?
- Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Working together
One painter painted the nursery in 10 days, the second in 8 days. How many days will the nursery be painted if they work together? - 7 men
Seven men can complete work in 52 days. How many days will 13 men finish the same work?