Mason with assistant
Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
Correct answer:
Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Assistant 39951
The worker performs the repair work in 20 days, and his assistant does the job himself in 60 days. How many days would they work together? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Together 8086
The first tiler would cover the inside of the pool in 5 working days, and the second would need seven working days for the same work. In how many days would they line the inside of the pool together? - Three workers
Three workers, A, B, and C, have to work on a specific task. Workers A and B completed the task in 12 days, B with C for 19 days, and A with C for 24 days. How long would it take to complete the task for everyone alone? How long would it take to complete
- Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together? - Two masons
Two masons built the garage together - it took 18 days. If they worked independently, the other would work 15 days more than the first. For how many days would build the garage each mason himself? - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Working together
Zeru can complete a certain job in 5 days, and Tulu can complete the same job in 3 days. How long will they complete the job if they work together?
- Production 24021
The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete - Painters 4
One painter will do the job for 12 days. After a 4 1/3 day, he comes second to help him complete work together for eight days. How long would work the second painter himself? - Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Technical 2617
Pupils work in groups of two on technical work in the school to make a birdhouse. If Tomáš worked alone, he would make the booth in 4 hours. Richard would do it in 2 hours. If they work together, how many hours will it take them to complete it? - Panel house
The construction company has two groups of workers. Group A has more members than B. Panel house was insulated by group A for ten days. They insulated the same block of flats together in 6 days. How many days would group B block insulate?
- Independently 12921
Factory A can fulfill the order independently in 10 days. Factory B fulfills the same order in 16 days. How many days will the order be completed if only plant B works on it for 3 days and then both plants together? - Together 82970
The first tiler would tile the pool inside in 5 working hours; the second would need 7 working hours for the same job. How long would it take them to tile the pool inside together if the second tiler starts working on the pool 12 minutes later than the fi - Working together
Two people will do the work in 12 days. They worked together for eight days. Then only one worked for ten days. How many days would each of them do the work if he worked alone?