Fifteen loggers would take 12 days to clear a large field. How many days did this work require, if 5 more woodcutters were transferred to them after 4 days of work?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Lumberjacks
Fifteen lumberjacks would take 12 days to destroy the broken trees. How many days would this work require if the company added five workers to it after four days? - Five tractors
Five tractors plow the field in 4.8 hours. How long would it take to plow this field if, after 1.5 hours of work, two tractors went to a different field? - Part-timers
Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours? - Complete 19783
Two roofers were to cover the roof in 14 days. After five days, they added one roofer. How long will it take them to complete the work? How many days will it take them to cover?
- Assemblers 47483
Two assemblers with the same daily output were to complete the assembly in 12 days. After 4 days, one of them got sick, and the other finished the assembly in another 16 days. How long would it take everyone to do the assembly by themselves? - Opportunities 8372
There are 20 students in the class, four of them are being tested by the teacher. How many options are there to choose who the teacher will test? - Together 7332
One tractor driver would mow the field in 15 hours. Another tractor driver would do the same job in 12 hours. How long will it take them to do the work together if the latter starts plowing two hours later than the former? - Equally 83095
John and Joseph carved the garden in 6 days. If an equally fast George joined them, how many days would it take them? - Our house
Our house would paint by four painters in 14 days. How long could it paint five painters? How long will it take if two other painters come to help after five days?
- Expedition 82407
Food for 56 sailors would last 32 days. How long did the food supplies last the expedition if 14 castaways were taken on board after 12 days of sailing? - Painters 81101
Four painters painted the house in 14 days. How long will it take if 2 more come to help after 5 days? - Switzerland 3584
Zuzka and Hanka used to work in a cherry orchard to earn money for a sightseeing trip to Switzerland. They brushed 15 trees every day and harvested the entire orchard in 10 days. How long would it take them to harvest the entire orchard if they brushed 20 - Construction 71794
Two different trucks together would bring the construction material in 6 hours. However, after 4 hours, the first car was transferred to another job, and the second one was driven for another 6 hours. How many hours would it take for the first car to deli - Woodcutter 39491
A bark beetle attacked part of the forest. The first woodcutter would need ten shifts to clear the forest, the second 6 shifts, and the third five shifts. Calculate how many shifts the forest will take if they work together.
- Efficient 43461
Four workers were supposed to build 200m of the fence in 15 days. However, after 3 days, two more workers came to their aid. All workers were equally efficient. Calculate how many meters of the fence (from the original 200m) remained after the first 3 day - Workers
Ten workers must pave road street for 22 working days. After four days were for speeding up work, added two more workers. a) After how many work days now workers complete the paved road? b) How many working days does a total paved road take? - Friends 81769
Four guys would finish washing cars at a gas station in 4 hours. After one hour, two more friends come to help them. How long will it take to finish the car wash?