Bricklayer work
A bricklayer will lay 12 m³ of brickwork in 4 days if he works 7 hours a day. How many days will he lay 51 m³ of masonry if he works 8.5 hours daily?
Final Answer:

Tips for related online calculators
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Nora works
Nora works 6.25 hours a day. If her hourly rate is 70.60 pesos, how much is she paid daily? - Directly proportional
A person earns directly proportional to the number of hours she works daily. If she works h hours one day and makes s dollars an hour, what is the total amount she earns for the day in terms of h and s? - The machine
The machine works 7 hours daily and produces 1 part in 5 minutes. How many parts will it produce in 1 hour? How many parts will it produce in 1 day? - A labourer
A laborer who works five days a week starts at 10 AM on Monday. If he works for 56 days, on which day will he complete the job? - Painting rooms
If Daniel paints for three hours daily, he completes it in 7.5 days. How many hours a day would he have to work to finish the job 1.5 days earlier? - Bricklayers
When a bricklayer works to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make three such houses together? - Mac worked
Mac worked for 8 hours and earned 897.6 pesos. How much will he earn if he works for 6.5 hours a day for a week?