Material supply
The material for 83 masons of the company is enough for 12 days. How many days will this supply be enough for them if the company has accepted six more masons?
Final Answer:

Tips for related online calculators
You need to know the following knowledge to solve this word math problem:
basic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Highway
Six trucks will be used to build the roadside for 18 days. After three days, the company sent two more trucks to make. How long will it take for the material to move? - Construction of the road
Six trucks are supposed to be transported for 18 days to construct the road dam. After three days, the transport company sent two more cars to the construction site. How long will it take to carry the material? - Specialist hiring probability
A private company will hire two IT specialists. Thomas is among the five registered candidates. What is the probability that he will not be accepted? - Deadline
Five equally skilled masons built half the wall in 14 days. They must build the remaining part in 6 days to catch the planned deadline. How many more masons need to be allocated for construction? - Performance
Two masons with the same performance would have been made of plaster for six days. One of them, however, has increased its daily performance by 50%. How long would it take them now to make plaster together? - Boiler room
If only the first boiler is running, the coal supply lasts 8 days. If only the second boiler is running, the supply lasts 12 days. If only the third boiler is running, the supply lasts 6 days. How many days in total will the coal supply last if only the f - Eight masons
Eight masons will plaster a wall with an area of 1440 m² in 9 days. They work 8 hours a day. How much area will plaster six masons in 4 hours?