Apprentice
The master helped the apprentice complete part of the task, the apprentice completed the rest himself. It turned out that the time needed to complete the task was three times shorter than if the apprentice had completed the task himself. How many times more time would the master need to complete the task himself compared to the time it took him to help the apprentice?
Final Answer:

Tips for related online calculators
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Cable division parts
The master gave the apprentice the task of dividing the 28 m long electric cable into two parts so that the second part was 2.5 times larger than the first. How long were the cable sections supposed to be? - Master work
The master will complete the given task in 4 hours. When they're done together, how long will it take to master students entirely in three hours? - Bricklayer apprentice wall
The bricklayer and the apprentice will build the wall in 6 hours. If the bricklayer worked alone, the wall construction would take him 5 hours shorter than the apprentice. How long before the wall would the bricklayer build himself? - Novak
Novak needed to dig up three of the same pit in the garden. The first pit was dug father alone for 15 hours. His second dig son helped him, and it did that in six hours. The third pit was dug son himself. How long does it take him? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Three workers
Three workers, A, B, and C, must work on a specific task. Workers A and B completed the task in 19 days, B with C for 19 days, and A with C for 11 days. How long would it take to complete the task for everyone alone? How long would it take to complete the - Mason shift sickness
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick. a) In how many more shifts did the masons complete the said plastering? b) In how many shifts was the assigned
