Mason with assistant
Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together, they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
Final Answer:

Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Apprentice
A master craftsman helped an apprentice complete part of a task, and the apprentice completed the rest himself. It turned out that the time needed to complete the task was three times shorter than if the apprentice had completed the entire task himself. H - Mason shift sickness
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick. a) In how many more shifts did the masons complete the said plastering? b) In how many shifts was the assigned - Mason house addition
8 masons build a house in 630 days. How many masons must we add after 150 days to complete the whole house in 320 days? - Worker repair time
The worker performs the repair work in 20 days, and his assistant does the job himself in 60 days. How many days would they work together? - Construction work
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Two companies
Two companies completed a job together in 100 days. The first company alone could complete the job in 150 days. How long would the second company take to complete the job alone? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked?