Mason with assistant
Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together, they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
Correct answer:

Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Assistant 39951
The worker performs the repair work in 20 days, and his assistant does the job himself in 60 days. How many days would they work together?
- Three workers
Three workers, A, B, and C, must work on a specific task. Workers A and B completed the task in 22 days, B with C for 10 days, and A with C for 19 days. How long would it take to complete the task for everyone alone? How long would it take to complete the
- Two masons
Two masons built the garage together—it took 18 days. If they worked independently, the other would have worked 15 days more than the first. How many days would it take each mason to build the garage alone?
- Together 8086
The first tiler would cover the inside of the pool in 5 working days, and the second would need seven working days for the same work. In how many days would they line the inside of the pool together?
- Apprentice
The master helped the apprentice complete part of the task, the apprentice completed the rest himself. It turned out that the time needed to complete the task was three times shorter than if the apprentice had completed the task himself. How many times mo
- Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together?
- Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked?