Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work. - Complete 5584
The two workers dug together for 6 hours. The first worker would do the work himself in 14 hours. How long would it take for the second worker to complete the task? - Adjusting 72554
Two working groups are adjusting the park. The first group would do the work in 15 days, and the second in 25 days. How many days will they do the work together? - Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job? - Two workers
Two workers together execute some work in 10 days. The first worker would have done it himself in 20 days. How many days would they have done himself a second worker? - Production 24021
The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete - Two companies
The family ordered two companies to modify the garden. The first would be done in 20 days; the second would take 40% less time. How long will they work together if the second company started working when the first worked for four days? - Three workers
Three workers, A, B, and C, have to work on a specific task. Workers A and B completed the task in 12 days, B with C for 19 days, and A with C for 24 days. How long would it take to complete the task for everyone alone? How long would it take to complete - Work
The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together. Then the first worker did the remaining work himself. In what proportion should the remuneration of the workers - Together 65074
Jana washes 20 windows alone in 4 hours. Petra would be able to do it in 6 hours. How long will it take to work together? - Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Panel house
The construction company has two groups of workers. Group A has more members than B. Panel house was insulated by group A for ten days. They insulated the same block of flats together in 6 days. How many days would group B block insulate? - Two workers
Two workers should fulfill specific tasks together for five days. If the first worker increased their performance twice and the second twice fell, it took them just four days. For how many days would he handle the entire task, the first worker himself? - Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c