The family ordered two companies to modify the garden. The first would be done in 20 days; the second would take 40% less time. How long will they work together if the second company started working when the first worked for four days?
Correct answer:

Tips for related online calculators
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Our percentage calculator will help you quickly calculate various typical tasks with percentages.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Our percentage calculator will help you quickly calculate various typical tasks with percentages.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Construction 7709
Two construction companies are working on the landscaping. The first would do the whole job in 12 days, the second in 20 days. How long will they work together if the first start working when the second has already worked 4 days?
- Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job?
- Engineering 54971
Two engineering companies have the same production program. The first company would fulfill their orders in 20 days. The second company in 16 days. How long will the companies fulfill the order if the first company starts working 2 days earlier?
- Workshops
The first workshop will do the robot itself in 15 days, and the second workshop in 10 days. They started together, but only the second workshop worked after three days. How many days will the work be done?
- Two companies
The two companies did work together for 100 days. The first company would do it in 150 days. How many days would the work take the second company?
- Digging
The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?
- Together 81046
Two painters are painting the factory fence together. If everyone worked alone, the first would finish the job in 16 days, the second in 20 days. When will they finish the work together?
- Three painters
The three painters have painted bridges. The first would work done in 5 days, the second in 6 days, and the third in 7.5 days. How long will the bridge work if they work together?
- Companies 4156
Company A mows the meadow in ten hours. Company B will cut the meadow with dynamite in six hours. How many hours would these companies mow two meadows if they worked together?
- Digging companies
Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days, and company D for 24 days. Work began together with companies C and D but after three days. They joined the other two companies. How long took to dig a pit?
- Workers
Two workers, A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finished the job alone for 7.5 days. If every worker was working alone, how many days took the whole work for workers
- Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet
- Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together?
- Boots
Master shoemaker has three apprentices. First, do one pair of boots for two days, second for one day, and third for 1.5 days. How long would it take to make a couple of boots if they worked together?
- Bricklayers
The first bricklayer would build a wall in 3 days, the second in 4 days. The first bricklayer worked alone for a day, then the second bricklayer came to his aid and finished the work together. How long did it take to build the wall?
- Work together
Two bricklayers are plastering a wall. The first would plaster it in 8 hours, the second in 12 hours. How many hours will they be done with the work if they work together?
- Adjusting 72554
Two working groups are adjusting the park. The first group would do the work in 15 days, and the second in 25 days. How many days will they do the work together?