Two masons

Two masons built the garage together - it took 18 days. If they worked independently, the other would work 15 days more than the first. For how many days would build the garage each mason himhelp?

Correct answer:

x =  30
y =  45

Step-by-step explanation:

1x+1y=118 y=x+15  1x+1x+15=118  18(2x+15)=x(x+15) x221x270=0  a=1;b=21;c=270 D=b24ac=21241(270)=1521 D>0  x1,2=b±D2a=21±15212 x1,2=21±392 x1,2=10.5±19.5 x1=30 x2=9   Factored form of the equation:  (x30)(x+9)=0  x>0 x=30
y=x+15=45



We will be pleased if You send us any improvements to this math problem. Thank you!






avatar




Tips to related online calculators
Looking for help with calculating roots of a quadratic equation?
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Working together
    workers Two people will do the work in 12 days. They worked together for 8 days. Then only one worked for 10 days. How many days would each of them do the work if he worked alone?
  • Workers
    two_workers Two workers A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  • Bricklayers
    murar The first bricklayer would build a wall in 3 days, the second in 4 days. The first bricklayer worked alone for a day, then the second bricklayer came to his aid and they finished the work together. How long did it take to build the wall?
  • Digging companies
    companies Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days and the company D for 24 days. Work began together companies C and D, but after three days joined them other two companies. How long took to dig a pit?
  • Two companies
    calendar The family ordered two companies to modify the garden. The first would be done in 20 days, the second would take 40% less time. How long will they work together if the second company started working when the first worked for 4 days?
  • Mason with assistant
    workers Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
  • Two workers
    workers Two workers should fulfill certain task together for 5 days. If the first worker increased their performance twice and second twice fell, it took them just four days. For how many days would handle the entire task first worker himself?
  • Painters
    painters The first team of painters would paint bridge in 15 days, the second in 10 days. After 3 days of working together second team goes out and continue only first team. How many days took second team to finish painting the bridge?
  • Two companies
    workers Company A can fulfill the order in 12 days, company B the same order in 18 days. How many days will the order be fulfilled if only company A works on it for the first two days, then the remaining days for both companies two?
  • Three people
    clocks Three people start doing a work at a same time. The first worked only 2 hours. The second ended 3 hours before the end. On an individual basis, it would take the first time to do the work 10 hours, second 12 hours and 15 hours third. How many hours did it
  • Deadline
    murar Five equally skilled masons built half the wall in 14 days. In order to meet the planned deadline, the remaining part must be built in 6 days. How many more masons need to be allocated for construction?
  • Digging
    digging The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?
  • Two diggers
    digging Two diggers should dig a ditch. If each of them worked just one-third of the time that the other digger needs, they'd dig up a 13/18 ditch together. Find the ratio of the performance of these two diggers.
  • Work
    workers The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Highway
    truck Six trucks will be used to build the roadside 18 days. After 3 days, two more trucks were sent to build. How long will it take for material move?
  • 3 masons
    cnb Three masons received 7,700 CZK. The second half received 1/2 more than the first and third twice more than the second mason. How much they each got crowns?
  • Together m+d
    painter Aunt Jane would paint her apartment in 10 hours, her mother in 15 hours. How much do they paint it for together?