Deadline

Five equally skilled masons built half the wall in 14 days. In order to meet the planned deadline, the remaining part must be built in 6 days. How many more masons need to be allocated for construction?

Correct answer:

n =  7

Step-by-step explanation:

5 14=(5+x) 6  6x=40  x=2036.666667  n=x=6.6667=7



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Two companies
    workers Company A can fulfill the order in 12 days, company B the same order in 18 days. How many days will the order be fulfilled if only company A works on it for the first two days, then the remaining days for both companies two?
  • Part-timers
    jahoda Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours?
  • Tractors
    tractor Six tractors plowing the field for 8 days. After two days, two tractors broke down. How many days were prolonged work in the field?
  • Two masons
    garage Two masons built the garage together - it took 18 days. If they worked independently, the other would work 15 days more than the first. For how many days would build the garage each mason himhelp?
  • Eight masons
    time Eight masons will plaster a wall with an area of 1440 m2 in 9 days. They work 8 hours a day. How much area will plaster 6 masons in 4 hours?
  • Six workers
    workers Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?
  • Mason with assistant
    workers Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
  • Working time
    work At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Painters
    natieraci Five painters painting the fence for eight days. How many days over will take work if paint the fence only four decorators?
  • The tank
    pipe2 The tank had 9 inflows to be filled in 21 days. After 9 days, 3 trips out. How many days did the remaining 6 tributaries fill the tank?
  • The orchard
    jablone 4 temporary workers harvested the orchard in 9 days. How many temporary workers we need for six days?
  • Diggers
    digging Eight diggers will do the job in 85 hours. After 21 hours, 3 diggers had to leave. How many hours will the work be done?
  • Five tractors
    tractors Five tractors plow the fields in 4.8 hours. How long will it take to plow the field when, after an hour and a half of work, two tractor drivers have been called up for another task?
  • Hectares of forest
    stromy 12 workers plant 24 ha of forest in 6 days. In how many days will 15 people and 12 people plant the same area?
  • Mr. Ben
    bricks Mr. Ben drives bricks to the construction site. If he drove three times a day, he would make bricks in 8 days. How many times a day would he go every day to be done 2 days earlier?
  • Work
    workers The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Bricklayers
    murar Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?