Complete 82405
8 masons build a house in 630 days. How many masons must we add after 150 days to complete the whole house in 320 days?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Bricklayers
Eight bricklayers build a house for 630 days. How many bricklayers have to add after 150 days to complete the whole building in (next) 320 days? - Bricklayers
Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days? - Deadline
Five equally skilled masons built half the wall in 14 days. They must build the remaining part in 6 days to catch the planned deadline. How many more masons need to be allocated for construction? - Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t
- Performance 66764
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick. a) In how many more shifts did the masons complete the said plastering? b) In how many shifts was the assigned - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - Tablecloths
The restaurant has sixty-two square tablecloths with a side length of 150 cm and 36 rectangular tablecloths with dimensions of 140 cm and 160 cm. A) How many meters of hemming ribbon will be needed if we add 50 cm to each tablecloth? B) The ribbon sale in - Workers
Ten workers must pave road street for 22 working days. After four days were for speeding up work, added two more workers. a) After how many work days now workers complete the paved road? b) How many working days does a total paved road take? - Two masons
Two masons built the garage together - it took 18 days. If they worked independently, the other would work 15 days more than the first. For how many days would build the garage each mason himself?
- PLUS MINUS product
A. Deduct 15.728 from the sum of 23.234 and 6.23 B. Add 15.756 to the difference of 26.845 and 4.342 C. Find the product of 0.86 x 0.05 D. Multiply 5.234 by 4.45 E What is the product of 23.97 multiplied by 6.36? - Alcohol
6l 48% alcohol, how much must we add 52% alcohol to give 50% alcohol? - Forestry workers
56 laborers have employed planted trees in the forest. For 8 hour work, a day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day? - Scientific notation mul
A student found the product of 8 × 10³ and 7 × 105 to be 5.6 × 108. What is the error? What is the correct product? Complete the explanation. - Z-score
The mean adult male pulse rate is 67.3 beats per minute, with a standard deviation of 10.3. Find the z-score for an adult male's pulse rate of 75. (Round the z-score to two decimal places. )
- Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Seamstresses 4635
Eight seamstresses have to complete the order in 16 days. After four days, the two seamstresses switched to another job. In how many days will the order be fulfilled? - Efficient 43461
Four workers were supposed to build 200m of the fence in 15 days. However, after 3 days, two more workers came to their aid. All workers were equally efficient. Calculate how many meters of the fence (from the original 200m) remained after the first 3 day