Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must they increase their performance on the third day to complete the building?
Correct answer:
Tips for related online calculators
Our percentage calculator will help you quickly calculate various typical tasks with percentages.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Grade of the word problem:
Related math problems and questions:
- Performance 66764
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick. a) In how many more shifts did the masons complete the said plastering? b) In how many shifts was the assigned - Performance 5041
Three workers received a reward of €2,850 for their work. They divided them according to their performance so that the first received 20% less than the second and the third received €50 more than the second. How many euros did each person receive? - Revitalization 39191
Workers are building a new sidewalk while revitalizing the housing estate. Six workers will do the work in 12 days, but this is a problem because the sidewalk must be completed in 10 days to complete the work on time. How many workers must be hired to com - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days?
- Foresters 81919
Foresters planted 2,440 saplings in three days. On the second day, they planted 20% more saplings than on the first day, and on the third day, 15% less than on the first day. How many saplings did the foresters plant each day? - Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together? - Repairing 80759
They spent three days repairing the damaged pipe, 115 m long. On the first day, they repaired a quarter of what they did on the second day, and on the third day, they repaired 20m less than on the second day. How many m of pipe did they repair on the firs