Construction work
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must they increase their performance on the third day to complete the building?
Final Answer:

Tips for related online calculators
Need help calculating a sum, simplifying, or multiplying fractions? Try our fraction calculator.
Our percentage calculator will help you quickly and easily solve a variety of common percentage-related problems.
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Our percentage calculator will help you quickly and easily solve a variety of common percentage-related problems.
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsnumbersUnits of physical quantitiesGrade of the word problem
Related math problems and questions:
- Mason shift sickness
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick. a) In how many more shifts did the masons complete the said plastering? b) In how many shifts was the assigned - A construction 2
A construction company will be penalized for its bridge construction delays. The penalty is set at 4,000 for the first day and shall be subjected to a 1,000 increase for each succeeding day. The company can afford a maximum payment of 165,000 for a penalt - Sidewalk worker
Workers are building a new sidewalk while revitalizing the housing estate. Six workers will do the work in 12 days, but this is a problem because the sidewalk must be completed in 10 days to complete the work on time. How many workers must be hired to com - Working group
20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? - Three workers
Three workers, A, B, and C, must work on a specific task. Workers A and B completed the task in 19 days, B with C for 19 days, and A with C for 11 days. How long would it take to complete the task for everyone alone? How long would it take to complete the - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Work in factory
45 men can complete a work in 16 days, but after some days they started working 30 more men joined them and completed the remaining work in 6 days. How many days after the commencement of the job did 30 men join?
