Performance 66764
Six masons of equal performance were able to plaster the walls of the new garages in 18 shifts. After 4 shifts of joint plastering, 2 got sick.
a) In how many more shifts did the masons complete the said plastering?
b) In how many shifts was the assigned task completely completed?
a) In how many more shifts did the masons complete the said plastering?
b) In how many shifts was the assigned task completely completed?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Construction 1639
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Two workers
The first worker would complete the work in 8 hours, the other in 6 hours. After two hours of joint work, the worker left the first worker to a doctor, and the others completed the work themselves. How many hours worked did the other worker himself? - Michael 6
Michael was assigned math problems to complete for his weekly homework. So far, he has completed 28 problems, which is 2/7 of the total number of math problems he was assigned. How many total math problems was Michael assigned for homework? - Two workers
The first worker completed the task by himself in 12 hours, and the second in 10 hours. After two hours of joint work left, the first worker went to a doctor, and the second finished the job himself. How many hours worked the second worker himself?
- Assemblers 47483
Two assemblers with the same daily output were to complete the assembly in 12 days. After 4 days, one of them got sick, and the other finished the assembly in another 16 days. How long would it take everyone to do the assembly by themselves? - Performance
Two masons with the same performance would have been made of plaster for six days. One of them, however, has increased its daily performance by 50%. How long would it take them now to make plaster together? - Continued 7310
In one workshop, they will do the given work in 15 days; in another workshop, where more members work, they will do the given work in 10 days. After three days of joint work, only the larger workshop continued the assigned work. In how many days will he f - Manuscript 54691
The typist was given the task of rewriting the manuscript of the adventure book in 8 days. However, she completed the task in 6 days because she rewrote 6 more pages per day than she was supposed to rewrite. Determine the number of pages of an adventure b - Plastered 2529
The mason was to be plastered in a shift of 24.2 m² of the wall. At what percentage did he meet the plan when plastered 306 m² walls in 12 shifts?
- Performance 31371
According to the plan, seven pavers were to pave the square in 14 days. After two days of work, another 5 pavers came to help them. How many days from the arrival of the pavers will the work be completed? (tile performance is the same) - Bricklayers 18773
According to the standard, we calculated that two masons would plaster the corridor of the new school building in 54 hours. How long would it take for nine bricklayers to plaster this corridor? - Complete 82405
8 masons build a house in 630 days. How many masons must we add after 150 days to complete the whole house in 320 days? - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked? - Six workers
Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate?
- Work together
Two bricklayers are plastering a wall. The first would plaster it in 8 hours, the second in 12 hours. How many hours will they be done with the work if they work together? - Installed 5793
A group of fitters installed the cable line in 9 changes, and the second group completed the same task in 1/3 less time. How many shifts would the third group do the same work if, with all three groups working together, the assembly took 2 shifts? - Seven
Seven dwarfs will cut 420 stumps in 15 hours. After five hours, the two dwarves disappear discreetly. How many hours will the remaining dwarves complete the task?