Two workers

The first worker would himself completed the work in 8 hours, the other in 6 hours. After two hours of joint work, the worker left the first worker to a doctor, and others completed the work himself. How many hours worked the other worker himself?

Correct answer:

t =  2.5 h

Step-by-step explanation:


2•(1/8 + 1/6) + t/6 = 1

4t = 10

t = 5/2 = 2.5

Our simple equation calculator calculates it.



We will be pleased if You send us any improvements to this math problem. Thank you!






avatar




Tips to related online calculators
Need help to calculate sum, simplify or multiply fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Two workers
    mame_nizke_mzdy The first worker completed the task by himself in 9 hours, the second in 15 hours. After two hours of joint work left first worker to a doctor and the second finished the job himself. How many hours worked second worker himself?
  • Work
    workers_21 The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Two workers
    Frog Two workers together execute some work in 10 days. The first worker would have done himself in 20 days. How many days would have done himself a second worker?
  • Gas pipeline
    clocks Worker Molnár excavated the gas pipeline in 15 hours, worker Lakatoš in 12 hours and worker Soukup in 10 hours. After how many hours of joint work will the excavation be completed?
  • Parquet floor
    Parkett Three workers laid parquet floor for 2.301 hour. The first one would do this work alone 7 hours, the second in 6 hours. For how many hours would fulfill this work the third worker, if he worked alone?
  • Workers
    workers Two workers fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will do whole job a second worker?
  • Two workers
    work One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the second was recalled, and the first completed the job itself in 5 hours. How many hours did they work together, and how much did
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Four workers
    wood_6 Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • Turners
    workers_25 Two turners perform joint work in 3 hours. The first turner would perform the job himself in 7 hours. How long would the same job last for a second turner if he worked alone?
  • Workers 2
    delnik Worker dug the trench for 7 hours, another worker for 10 hours. They recruited to work even one worker more. Digging should be done for 2 hours. For how long would dig third worker alone?
  • Two friends
    clock-night-schr_13 Peter can do all his work himself in 6 hours. Martin can do the same work himself in 8 hours. Peter worked first and then replaced by Martin. Whole work was done in 6.5 hours. Calculate how long Peter worked before replaced by Martin.
  • Apprentice
    ucen Worker and apprentice execute the work for 6 hours. The worker performs himself in 10 hours. How long do the work of an apprentice?
  • Diggers
    workers_1 The excavation was carried out in 4 days and 5 workers worked on it for 7 hours a day. Determine how long it would take to excavate if 7 workers worked on it 8 hours a day.
  • Forestry workers
    forestry_workers In the forest is employed 56 laborers planting trees in nurseries. For 8 hour work day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day?
  • Insulation
    zateplovanie-domu Two workers insulate the house in 5 days. After the first day of working together, only one worker continue to cover the house. In how many days will the house be insulated if every worker has the same tempo of work?
  • Tributaries
    inlets We can fill the pool with two different tributaries. The first inflow would fill the pool in 18 hours, both in 6 hours. How many hours would the pool fill with a second inflow?