Two workers

One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the second was recalled, and the first completed the job itself in 5 hours. How many hours did they work together, and how much did each of them do?

Correct answer:

x =  15 h
a =  0.5
b =  0.5

Step-by-step explanation:

x (1/40+1/30)+5/40=1  7x=105  x=15=15 h
a=x+540=15+540=12=0.5
b=x30=1530=12=0.5



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar







Tips to related online calculators
Need help to calculate sum, simplify or multiply fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Two workers
    clock-night-schr The first worker would himself completed the work in 8 hours, the other in 6 hours. After two hours of joint work, the worker left the first worker to a doctor, and others completed the work himself. How many hours worked the other worker himself?
  • Two workers
    mame_nizke_mzdy The first worker completed the task by himself in 9 hours, the second in 15 hours. After two hours of joint work left first worker to a doctor and the second finished the job himself. How many hours worked second worker himself?
  • Trucks
    truck_big Truck take you the some amount of clay in 30 hours. Second truck in 40 hours. Trucks carted the clay away some time together then the second truck broke down and the first one completed the job in five hours. What time worked together?
  • Work
    workers The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Workers
    two_workers Two workers A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  • Workers 2
    delnik Worker dug the trench for 7 hours, another worker for 10 hours. They recruited to work even one worker more. Digging should be done for 2 hours. For how long would dig third worker alone?
  • Gas pipeline
    clocks Worker Molnár excavated the gas pipeline in 15 hours, worker Lakatoš in 12 hours and worker Soukup in 10 hours. After how many hours of joint work will the excavation be completed?
  • Workers
    workers Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will do the whole job a second worker?
  • Parquet floor
    Parkett Three workers laid the parquet floor for 2.301 hour. The first one would do this work alone 7 hours, the second in 6 hours. For how many hours would fulfill this work the third worker if he worked alone?
  • Two workers
    2workers Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker next half of the work it will take 25 hours. How long would it take job them separately?
  • Road repair
    workers Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  • Mukls
    Chinese women workers The working group, in which 6 workers would ordered job completed within 21 working days. How many workers must be accept yet that the contract will be completed in 14 working days?
  • Turners
    workers Two turners perform joint work in 3 hours. The first turner would perform the job himself in 7 hours. How long would the same job last for a second turner if he worked alone?
  • Digging
    digging The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Two friends
    clock-night-schr Peter can do all his work himself in 6 hours. Martin can do the same work himself in 8 hours. Peter worked first and then replaced by Martin. Whole work was done in 6.5 hours. Calculate how long Peter worked before replaced by Martin.
  • Welders
    svarec Welder do the job for six hours, the second one for 8 hours. How long do the job third welder if all together can do job in 2 hours?