Mow the lawn

Dano would mow the lawn in 12 hours and Milada in 16 hours. How long will take the lawn mow together?

Result

t =  6.857 h

Solution:

Solution in text t =







Leave us a comment of this math problem and its solution (i.e. if it is still somewhat unclear...):

Showing 0 comments:
1st comment
Be the first to comment!
avatar




To solve this verbal math problem are needed these knowledge from mathematics:

Looking for help with calculating harmonic mean? Looking for a statistical calculator?

Next similar math problems:

  1. Three painters
    workers_37 The three painters have painted bridge. The first would work done in 5 days, the second in 6 days, and the third in 7.5 days. How long will the bridge work if they work together?
  2. Dwarfs
    trpaslik Four dwarfs would prepare firewood for Snow White in580 minutes. After an hour and a half they recruit friends so that finished preparing the wood for 280 minutes. How many dwarfs they recruited?
  3. Harvesters
    kombajn_10 The first harvester will harvest the grain from the field in 20 hours, the second, the more powerful in 10 hours. How long will take harvest this field by both harvesters, if the second harvester has to be set up first and this takes 2 hours? The first har
  4. Together 3
    painter_8 If Sally can paint a house in 4 hours, and John can paint the same house in 6 hours, how long will it take for both of them to paint the house together?
  5. Workers
    okno2_1 Group of workers washing half of the windows of the building in two hours. How long will take half the workers wash all the windows of the building?
  6. Two diggers
    two-diggers There are two diggers. One digger digs a pit 46 hours second gidding 2 times faster. a) how long took to dig a pit second digger b) how long took dig together
  7. Pumping
    pumps_1 The tank is filled with a larger pump in 12 hours and with scond pump in 15 hours. For how long does the tank fill when both pumps are switched on at the same time?
  8. Apprentice
    ucen Worker and apprentice execute the work for 6 hours. Worker performs himself in 10 hours. How long do the work of an apprentice?
  9. Soldier
    digging_1 An experienced soldier digs a good trench in 30 hours. Two soldiers dug the same trench each 40 hours. How many hours will the ditch dig all three together?
  10. Bricklayers
    delnik_4 When a bricklayer works himself to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make 3 such houses together?
  11. Construction of road
    truck_14 For the construction of the road dam, it is supposed to transport six trucks a total of 18 days. After three days, two more cars were sent to the construction site. How long will it take to carry the material?
  12. Hectoliters of water
    pumps_7 The pool has a total of 126 hectoliters of water. The first pump draws 2.1 liters of water per second. A second pump pumps 3.5 liters of water per second. How long will it take both pumps to drain four-fifths of the water at the same time?
  13. Flowerbed
    flowers_9 Ondra digs the bed in 20 minutes. Cuba in 30 minutes. For how long do they dig together?
  14. Working together on project
    work_10 Two employees working on the project. First make it alone for 20 days the second for 24 days. How many days will take to complete project if 5 days they work together then first will take two days holiday and after returning they completes a project toget
  15. Workers
    workers Two workers fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will do whole job a second worker?
  16. The factory
    clocks_13 The factory z can complete an order in 12 days, factory p in 18 days. For how many days does an order completed when the first two days work only the factory z and then both factories?
  17. Christmas Day
    stedryd In leap years was 53 Sundays. On what day of the week fell to Christmas Day?