Six painters paint an area of 120 m2 in 4 hours. How long does it take for 12 painters to paint 480 m2 with the same performance?

Correct answer:

t =  8 h

Step-by-step explanation:

a=120/(6 4)=5 m2/h/m  t=48012 a=48012 5=8 h



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar







Tips to related online calculators
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Together 3
    painter If Sally can paint a house in 4 hours, and John can paint the same house in 6 hours, how long will it take for both of them to paint the house together?
  • Painters
    malovka2 Six of the painters paint 90 m of the fence in five hours. For how long would the four painters paint a 45-meter fence? How many meters fence painted painters 5 for two hours?
  • Machines
    machinery In the workshop are three machines. The first is treated 250 parts for 4.7 hours, the second is treated 300 parts for 1.9 hours, and the third is treated 230 parts for 4.6 hours. How long will it take to make 3100 parts if worked all three machines at the
  • Workers
    work 9 workers dig a canal 120 meters long for eight hours. For how long would be dig five workers canal 200 meters long?
  • Painters
    time Ten painters paint the school in 20 days. How many days do four painters paint the school at the same pace of work?
  • Painters
    3_painters One painter could paint a school for seven days. The second one does it for six days. It was necessary to paint the school in two days. The next painter was invited, and all worked together. How long would this painter paint the school itself?
  • Four painters
    painter The company sent four painters to paint the school. They should be done in 12 days. After three days, one painter got ill. How long will the remaining painters paint the school?
  • The ABCD
    trapezium The ABCD trapezoid has a base length of a = 120mm, c = 86mm and an area of S = 2575 mm2. Calculate the height of the trapezoid.
  • Two pumps
    nadrz The first pump fills the tank in 24 hours second pump in another 40 hours. For how long will it take to fill the tank if it operates both pumps at the same time?
  • Three
    work Three pavers will pave the sidewalk in 4 days. How long does it take for two tiles to pave the same sidewalk?
  • Four workers
    wood Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • A trapezoid 3
    trapezium A trapezoid ABCD has the bases length of a = 120 mm, c = 86 mm and the area A = 2,575 mm2. Find the height of the trapezoid.
  • Grass
    minutes_clock Peter and Stano lawn grass for 3 hours 12 minutes. How long would it take to Peter if Stano lawn grass himself for 384 minutes.
  • Painters
    maliri Fifteen painters painted the fence for 280 minutes. For how many minutes paint half of this fence 12 painters?
  • Our house
    malovka Our house would paint four painters in 14 days. How long could it paint five painters? How long will it take if two other painters will come to help after 5 days?
  • Painters
    natieraci Five painters painting the fence for eight days. How many days over will take work if paint the fence only four decorators?
  • Painters
    painter First painter painted fence himself for 4 hours, the second painter 1.2 hours sooner than first, and the third painters slowest up to 16 hours. How long took them paint fence if worked together?