Five painters painting the fence for eight days. How many days over will take work if paint the fence only four decorators?

Correct answer:

x =  2 d

Step-by-step explanation:

a=5 8/4=10 x=a8=108=2 d



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar




Tips to related online calculators
Do you want to convert time units like minutes to seconds?

Related math problems and questions:

  • Painters
    time Ten painters paint the school in 20 days. How many days do four painters paint the school at the same pace of work?
  • Our house
    malovka Our house would paint four painters in 14 days. How long could it paint five painters? How long will it take if two other painters will come to help after 5 days?
  • Four painters
    painter The company sent four painters to paint the school. They should be done in 12 days. After three days, one painter got ill. How long will the remaining painters paint the school?
  • Painters
    malovka2 Six of the painters paint 90 m of the fence in five hours. For how long would the four painters paint a 45-meter fence? How many meters fence painted painters 5 for two hours?
  • Painters
    painters The first team of painters would paint bridge in 15 days, the second in 10 days. After 3 days of working together second team goes out and continue only first team. How many days took second team to finish painting the bridge?
  • Hectares of forest
    stromy 12 workers plant 24 ha of forest in 6 days. In how many days will 15 people and 12 people plant the same area?
  • Working time
    work At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Painting rooms
    palma If Dano paints three hours daily, he complete in 7.5 days. How many hours a day would have to work to finish the job 1.5 days earlier?
  • Painters
    painter First painter painted fence himself for 4 hours, the second painter 1.2 hours sooner than first, and the third painters slowest up to 16 hours. How long took them paint fence if worked together?
  • Wood harvesting
    woord The harvested wood is bundled from the forest to a sawmill. The driver makes the journey four times a day, and the work takes him 8 days. How many times would he have to go daily to get the job done 2 days earlier?
  • Tractors
    tractor Six tractors plowing the field for 8 days. After two days, two tractors broke down. How many days were prolonged work in the field?
  • Lumberjacks
    stromy Fifteen lumberjacks would take 12 days to destroy the broken trees. How many days would this work require if 5 workers added to it after 4 days?
  • Six painters
    painter Six painters paint an area of 120 m2 in 4 hours. How long does it take for 12 painters to paint 480 m2 with the same performance?
  • Painters 4
    painter One painter will do the job for 12 days. After a 4 1/3 day, he comes second to help him complete work together for eight days. How long would work the second painter himself?
  • Five tractors
    tractors Five tractors plow the fields in 4.8 hours. How long will it take to plow the field when, after an hour and a half of work, two tractor drivers have been called up for another task?
  • Part-timers
    jahoda Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours?
  • Working together
    malovka One painter paint the nursery in 10 days, the second in 8 days. How many days will the nursery be painted if they work together?