Ten identical trucks will take 240 tons of concrete to build the dam in 3 working days. How many tons of concrete will seven trucks take to make the dam in 5 days?
Correct answer:
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Highway
Six trucks will be used to build the roadside for 18 days. After three days, the company sent two more trucks to make. How long will it take for the material to move? - Construction of road
For the construction of the road dam, it is supposed to transport six trucks for 18 days. After three days, the transport company sent two more cars to the construction site. How long will it take to carry the material? - Embankment 56451
Twenty men will build a dam in 36 days if they work 10 hours daily. How many hours a day do 30 men have to work if the embankment is to be completed in 16 days? - Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet
- Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work. - Bricklayers
Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days? - 3 men
Three men painting a house take 7 1/2 days. How long will 5 men take over the same job? Working at the same rate. - One press
One press will produce one truck of respirators in 3.5 days. The second in 10 days. How long does it take to fill a truck while working together? - Wall builders
If 12 men can build a wall 398 meters long in 48 days, how long would it take 33 men to build a wall 347 meters long? Answer to 3 decimal places.
- Building a wall
If 12 men can build a wall 398 meters long in 48 days, how long would it take 33 men to build a wall 347 meters long? Answer to 3 decimal places. - Planting 27201
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f - Two companies
The family ordered two companies to modify the garden. The first would be done in 20 days; the second would take 40% less time. How long will they work together if the second company started working when the first worked for four days? - Birdhouse 12941
Michal would make a birdhouse in three hours, and Richard would make it in two hours. If they work together, how many hours will it take them to complete it? How much percent more time compared to the time of working together would Michal make the booth b - Amount 64464
There are 12,000 tons of coal on the first dome and 2,200 tons on the second. They take 80 tons from the first kick every day and 60 tons from the second. How many days will the same amount of coal be on both kicks?
- Materials 4405
Two trucks were supposed to load the building materials in 10 days. After 6 days of work, the first car broke down, and the second one carried building materials for another 9 days. How many days would the first and second cars take the building materials - Bricklayers
When a bricklayer works to redeem the house in 8 days, the other bricklayer will be finished in 10 days. How long will it take to make three such houses together? - Reconstructing 23991
Three groups take turns reconstructing one piece of highway. The first group would finish the job themselves in 40 working days. The second group is in 24 working days, and the third group is in 30 working days. How many days do you do it together?