Wall builders

If 12 men can build a wall 398 metres long in 48 days, how long would it take 33 men to build a wall 347 metres long? Answer to 3 decimal places.

Correct answer:

t =  15.218 d

Step-by-step explanation:

m=398/(12 48)=1992880.691  t=347/(33 m)=347/(33 0.691)=15.218 d



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar







Tips to related online calculators
Do you want to convert length units?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Bricklayers
    murar Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?
  • Bricklayers
    murar The first bricklayer would build a wall in 3 days, the second in 4 days. The first bricklayer worked alone for a day, then the second bricklayer came to his aid and they finished the work together. How long did it take to build the wall?
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta
  • The bricklayer
    murar The bricklayer built a six-meter base of the fence in 3 hours. How long does it take to build a 14 m long base?
  • Five pumps
    nadrz The water tank is filled with two pumps in 48 minutes. How long would it take to fill it with 5 same pumps?
  • The work
    clock-night-schr The work was to be done by 150 workers. At the beginning of their work, their number reduced by 40, which increased the time of work by 5 and 1/3 of the schedule. How long did work take?
  • Three
    work Three pavers will pave the sidewalk in 4 days. How long does it take for two tiles to pave the same sidewalk?
  • Three workshops
    workers One workshop can complete the task in 48 days, the second in 30 days and the third in 20 days. In how many days would the task be completed if all workshops worked?
  • Part-timers
    jahoda Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours?
  • Grass
    minutes_clock Peter and Stano lawn grass for 3 hours 12 minutes. How long would it take to Peter if Stano lawn grass himself for 384 minutes.
  • Brick wall
    plot_zed Garden 70 m long and 48 m wide should surround with wall 2.1 meters high and 30 cm thick. Wall will be built on the garden ground. How many will we need bricks if to 1 m³ is required approximately 300 bricks?
  • Triangles
    triangles Find out whether given sizes of the angles can be interior angles of a triangle: a) 23°10',84°30',72°20' b) 90°,41°33',48°37' c) 14°51',90°,75°49' d) 58°58',59°59',60°3'
  • Lumberjacks
    stromy Fifteen lumberjacks would take 12 days to destroy the broken trees. How many days would this work require if 5 workers added to it after 4 days?
  • Divisible by 5
    175px-5th_MarDiv How many three-digit odd numbers divisible by 5, which are in place ten's number 3?
  • Strawberries
    jahoda Three people pick strawberries from 48 rows in 8 hours. How many hours do five people need to pick strawberries from 20 rows?
  • Inflow - outflow
    water_barrels The tank will fill by inflow for 143 minutes and empties by outflow for 150 minutes. How long take to fill tank if it is also opened the inflow and outflow?
  • Reading records
    clock-night-schr Lucy, Tereza, and Petra decided to compile the compulsory reading records together. It would take 30 days for Lucia alone, 36 for Tereza and 45 for Petra. How long will it take to make records if they will work together?