Men at work

8 men can finish a piece of work in 40 days. If 2 more men joined with them, then how many days it will take to complete the work?

Correct answer:

t2 =  32

Step-by-step explanation:

w=8 40=320 md  t2=2+8w=2+8320=32



Did you find an error or inaccuracy? Feel free to write us. Thank you!