Work in factory
45 men can complete a work in 16 days, but after some days they started working 30 more men joined them and completed the remaining work in 6 days. How many days after the commencement of the job did 30 men join?
Final Answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Working group
20 men complete one third of a piece of work in 20 days. How many additional men should be employed to finish the rest of the work in 25 more days? - Manday, manhour
Job problem: 10 men can make 20 toys in 12 days working 12 hours a day.Then, in how many days can 24 persons make 32 toys working 16 hours a day? - Common work
39 men can repair a road in 12 days working 5 hours a day. How many days will be required to complete the same work with 30 men working 6 hours a day? - Men at work
8 men can finish a piece of work in 40 days. If 2 more men joined with them, then how many days it will take to complete the work? - A contractor 2
A contractor has to complete his contract in 92 days. 234 men were set to do the work, each of them works for 16 hours/day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, ea - Work
The first paving machine can pave a pavement in 28 hours, and the second in 26 hours. The first machine started working, and after 2 hours the second machine joined it. How long after the second machine starts will they finish the job together? - Working together
Zeru can complete a certain job in 5 days, and Tulu can complete the same job in 3 days. How long will they complete the job if they work together?