Work

The first paving machine can pave a pavement in 28 hours, and the second in 26 hours. The first machine started working, and after 2 hours the second machine joined it. How long after the second machine starts will they finish the job together?

Final Answer:

x =  14.5 h

Step-by-step explanation:

a=28 h b=26 h  A=a1=2810.0357 1/h B=b1=2610.0385 1/h  s=A+B=0.0357+0.0385=364270.0742 1/h  2 A+(x2) s=1 2 0.035714285714286+(x2) 0.074175824175824=1  0.074176x=1.076923  x=0.074175821.07692308=14.51851852  x=2739214.518519=14.5 h



Help us improve! If you spot a mistake, please let let us know. Thank you!







Tips for related online calculators
Check out our ratio calculator.
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

algebrabasic operations and conceptsUnits of physical quantitiesGrade of the word problem

Related math problems and questions: