Sick
Six seamstresses should make 60 shirts in five business days. After three days, two seamstresses were sick. How many days have the remaining seamstresses to finish the contract?
Correct answer:

Tips for related online calculators
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Sick colleague
All the classrooms at school were painted during the holidays. On the first day, 6 painters did one sixth of the required work. From the second day until the painting was finished, only 5 painters worked because one of them got sick. All the painters work
- Insulating a house
Five workers are working on insulating a house at such a pace that they could finish the job in 18 days. After three days of work, two workers were called away to another construction site. In how many days will the remaining workers finish the job?
- Six workers
Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate?
- I have 3
I have 67 shirts to wash. Seven were put in a machine. And shered 60 to 5 each girl to wash. How many did 5 each wash?
- Seamstresses 4635
Eight seamstresses have to complete the order in 16 days. After four days, the two seamstresses switched to another job. In how many days will the order be fulfilled?
- Construction 82411
It should have taken four trucks 6 hours and 45 minutes to bring the sand to the construction site. After 90 minutes, one car broke down. How long did it take to transport the remaining sand in three trucks?
- A contractor 2
A contractor has to complete his contract in 92 days. 234 men were set to do the work, each of them works for 16 hours/day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, ea