Six workers

Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate?

Final Answer:

t =  4.5 d

Step-by-step explanation:

6 5=6 2+(62) t  4t=18  t=418=4.5  t=29=4.5=4.5 d