Six workers

Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?

Correct answer:

t =  4.5 d

Step-by-step explanation:


6•5 = 6•2 + (6-2)•t

4t = 18

t = 9/2 = 4.5

Our simple equation calculator calculates it.



Did you find an error or inaccuracy? Feel free to write us. Thank you!






avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Repair pipe
    workers 20 workers had to repair broken pipes in 30 days. After fourteen days, four laborers joined them. How long did the pipe repair work last?
  • Sick
    kosela Six seamstresses should make 60 shirts in five business days. After three days two seamstresses were sick. How many days have the remaining seamstresses to finish contract?
  • Four workers
    wood Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • Road repair
    workers Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  • Our house
    malovka Our house would paint four painters in 14 days. How long could it paint five painters? How long will it take if two other painters will come to help after 5 days?
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta
  • Deadline
    murar Five equally skilled masons built half the wall in 14 days. In order to meet the planned deadline, the remaining part must be built in 6 days. How many more masons need to be allocated for construction?
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Mason with assistant
    workers Mason had to complete the work in 10 days. Two and a half days later, his assistant arrived. Together they completed the work in the next three and a half days. How many days would he need an assistant for the same work?
  • Insulation
    zateplovanie-domu Two workers insulate the house in 5 days. After the first day of working together, only one worker continue to cover the house. In how many days will the house be insulated if every worker has the same tempo of work?
  • The tank
    pipe2 The tank had 9 inflows to be filled in 21 days. After 9 days, 3 trips out. How many days did the remaining 6 tributaries fill the tank?
  • Four painters
    painter The company sent four painters to paint the school. They should be done in 12 days. After three days, one painter got ill. How long will the remaining painters paint the school?
  • Work
    workers The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Painters 4
    painter One painter will do the job for 12 days. After a 4 1/3 day he comes second to help him and complete work together for 8 days. How long would work the second painter himself?
  • Work at plant
    workers Handyman has vowed to do repair work at the plant for 25 days. However, work had to be shortened and therefore gained helper. Together they made all the corrections for 13 1/3 days. How long the work would take helper himself?
  • Bricklayers
    murar Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?
  • Workers
    workers Two workers fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will do whole job a second worker?