Assembly sick worker
Two assemblers with the same daily output were to complete the assembly in 12 days. After 4 days, one of them got sick, and the other finished the assembly in another 16 days. How long would it take everyone to do the assembly by themselves?
Final Answer:

Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Do you have a system of equations and are looking for calculator system of linear equations?
Do you want to convert time units like minutes to seconds?
Looking for a statistical calculator?
Do you have a system of equations and are looking for calculator system of linear equations?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
statisticsalgebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Flu epidemic
During the flu epidemic, 10% of the school's students fell ill on Monday, another 39 on Tuesday, and one-eighth of all the school's students joined them on Wednesday. During these three days, one-third of all school pupils fell ill. How many students does - Six workers
Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate? - Peter 13
Peter and Paul finished the first round of orders in 3 hours and 15 minutes. Peter, however, works a lot faster than Paul does; Peter is 2 and a half times as fast as Paul. For the second day of shipping orders, peter is unavailable; paul will have to do - Repairman
A repairman promised to complete repair work at the plant in 25 days. However, the work had to be shortened, so he took on a helper. Together, they finished all the repairs in a full day. How long would the helper take to do the work alone? - Sick colleague
All the classrooms at school were painted during the holidays. On the first day, 6 painters completed one sixth of the required work. From the second day until the painting was finished, only 5 painters worked because one of them fell ill. All painters wo - Seamstress work
Eight seamstresses have to complete the order in 16 days. After four days, the two seamstresses switched to another job. In how many days will the order be fulfilled? - Sow barley
Farmers wanted to sow barley within 13 days. Due to the excellent weather, they exceeded the daily plan of sowing by 2 ha and, therefore, finished sowing grain in 12 days. How many hectares of land did they sow with barley?