Roofer work completion
Two roofers were to cover the roof in 14 days. After five days, they added one roofer. How long will it take them to complete the work? How many days will it take them to cover?
Final Answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Roofer roof days
Three roofers cover a third of the roof in 10 days. In how many days would 5 roofers cover the entire roof at the same rate? - Roofer work completion
Three roofers put the roofing on the roof in 8 days. How long will it take to get two more after three days? - Six workers
Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate? - Technicians Work Days
The order required six technicians to complete it in 18 days. How long will it take for one, two, three, four, five, six, eight, ten, and twenty technicians to complete it? - Glove order
Four apprentices worked on a glove order for 20 days. How long would it take for eight apprentices to complete the contract in the same job? - Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - Bricklayers
Eight bricklayers build a house for 630 days. How many bricklayers must be added after 150 days to complete the building in (next) 320 days?