Workers
Ten workers must pave the road for 22 working days. After four days were spent speeding up work, two more workers were added.
a) After how many work days do workers complete the paved road?
b) How many working days does a total paved road take?
a) After how many work days do workers complete the paved road?
b) How many working days does a total paved road take?
Correct answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert velocity (speed) units?
Do you want to convert time units like minutes to seconds?
Do you want to convert velocity (speed) units?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Workers 4168
Ten workers managed to repair the road in 22 days. After four days, two more workers joined to speed up the work. How many days does it take to repair the road?
- Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days?
- Complete 19783
Two roofers were to cover the roof in 14 days. After five days, they added one roofer. How long will it take them to complete the work? How many days will it take them to cover?
- Paving 2
It will take a construction company 8 working days to pave the sidewalks on two streets in a city if all 6 pavers work. However, only 4 pavers can complete the job because the other two have been dismissed. How many working days will it take the group of
- 20-meter-long 39603
Two workers will pave a 20-meter-long sidewalk in 5 days. Determine how long it would take to pave the sidewalk: a) 4 workers b) 5 workers c) 10 workers
- Working together on project
Two employees did working on the project. First, make it alone for 20 days, the second for 24 days. How many days will it take to complete the project if five days they work together, then first will take two days holiday, and after returning they complet
- Bricklayers
Eight bricklayers build a house for 630 days. How many bricklayers must be added after 150 days to complete the building in (next) 320 days?