Workers

Ten workers must pave road street for 22 working days. After four days were for speeding up work added two more workers.

a) After how many work days now workers completes the paved road?
b) How many working days it took a total paved road?

Correct answer:

a =  15
b =  19

Step-by-step explanation:


4/22 + a•12/(10•22) = 1
b = a + 4

1.2a = 18
a-b = -4

a = 15
b = 19

Our linear equations calculator calculates it.



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar







Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert velocity (speed) units?
Do you want to convert time units like minutes to seconds?

Related math problems and questions:

  • Workers
    two_workers Two workers A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  • Mukls
    Chinese women workers The working group, in which 6 workers would ordered job completed within 21 working days. How many workers must be accept yet that the contract will be completed in 14 working days?
  • Working together on project
    work Two employees working on the project. First make it alone for 20 days the second for 24 days. How many days will take to complete project if 5 days they work together then first will take two days holiday and after returning they completes a project toget
  • Six workers
    workers Six workers earned a total of CZK 12,600 per week on the construction site (5 working days). How much do 7 workers earn in 10 days with the same daily average salary?
  • Road repair
    workers Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta
  • Two workers
    workers Two workers will do certain work for 12 days. After 8 days of working, was one removed, and then the other finished the job alone in 10 days. For how many days would do this work alone for each worker?
  • Working together
    workers Two people will do the work in 12 days. They worked together for 8 days. Then only one worked for 10 days. How many days would each of them do the work if he worked alone?
  • Two workers
    Frog Two workers together execute some work in 10 days. The first worker would have done himself in 20 days. How many days would have done himself a second worker?
  • Working time
    work At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Workers
    workers Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will do the whole job a second worker?
  • Painting school
    painting Redecoration school had scheduled for four crew to 10 days. After two days a single worker ill. For how many days the school was painted when remain workers working with the same tempo?
  • Two workers
    workers Two workers should fulfill certain task together for 5 days. If the first worker increased their performance twice and second twice fell, it took them just four days. For how many days would handle the entire task first worker himself?
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Forestry workers
    forestry_workers In the forest is employed 56 laborers planting trees in nurseries. For 8 hour work day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day?
  • Working together
    workers One worker performs work in 3 days, the second in 5 days. How much do they work together?
  • Workhorses
    work A team of colleagues done the work in 20 days. After adding 2 colleagues from the beginning the work was completed in 15 days. How many members has the colleague team?