Paving 2
It will take a construction company 8 working days to pave the sidewalks on two streets in a city if all 6 pavers work. However, only 4 pavers can complete the job because the other two have been dismissed. How many working days will it take the group of 4 pavers to pave the sidewalks?
Correct answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work.
- Three
Three pavers will pave the sidewalk in 4 days. How long does it take for two tiles to pave the same sidewalk?
- Working group
20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days?
- Remaining 82419
Seven pavers would pave the square in 15 shifts. After five shifts, two pavers fell ill. How long will it take for the remaining pavers to finish the job?
- Working together
Zeru can complete a certain job in 5 days, and Tulu can complete the same job in 3 days. How long will they complete the job if they work together?
- Apprentices 30051
Four apprentices worked on a glove order for 20 days. How long would it take for eight apprentices to complete the contract in the same job?
- Workers
Ten workers must pave the road for 22 working days. After four days were spent speeding up work, two more workers were added. a) After how many work days do workers complete the paved road? b) How many working days does a total paved road take?