Harvested 81719

Eight hop pickers harvest in 24 days. How many more pickers must be hired if the hops need to be harvested in 16 days?

Correct answer:

x =  4

Step-by-step explanation:

8 24=(8+x) 16  16x=64  x=1664=4  x=4



Did you find an error or inaccuracy? Feel free to write us. Thank you!