Workers 3291
The broad workers will do the job in 22.5 days. How many workers still need to be hired to do the job seven days earlier?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Revitalization 39191
Workers are building a new sidewalk while revitalizing the housing estate. Six workers will do the work in 12 days, but this is a problem because the sidewalk must be completed in 10 days to complete the work on time. How many workers must be hired to com - Twenty-seven 3476
Twenty-seven workers did the work in 12 days. In how many days would nine workers do the same job? - Harvested 81719
Eight hop pickers harvest in 24 days. How many more pickers must be hired if the hops need to be harvested in 16 days? - Workers
Two workers, A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finished the job alone for 7.5 days. If every worker worked alone, how many days did the whole work take for workers A
- Workers
Two workers would fulfill a certain task when working together for 10 days, the first if he worked himself done work in 17 days. How many days will the second worker do the whole job? - Two workers
Two workers will do certain work for 12 days. After eight days of working, one was removed, and the other finished the job alone in 10 days. For how many days would you do this work alone for each worker? - Workers 82802
Five workers do a job in 20 hours. How long will it take two workers to do the same job?