Part-timers 6344
Certain work was to be done by 21 workers during an eight-hour workday, due in 12 days. After five days, temporary workers came to their aid. They all worked together for 7 hours a day and finished the job in 6 days. How many part-timers were there?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Workers
Two workers, A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finished the job alone for 7.5 days. If every worker was working alone, how many days took the whole work for workers - Part-timers
Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours? - Bricklayers
The first bricklayer would build a wall in 3 days, the second in 4 days. The first bricklayer worked alone for a day, then the second bricklayer came to his aid and finished the work together. How long did it take to build the wall? - Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job?
- Efficient 43461
Four workers were supposed to build 200m of the fence in 15 days. However, after 3 days, two more workers came to their aid. All workers were equally efficient. Calculate how many meters of the fence (from the original 200m) remained after the first 3 day - Two workers
Two workers will do certain work for 12 days. After eight days of working, one was removed, and the other finished the job alone in 10 days. For how many days would you do this work alone for each worker? - Two workers
The first worker completed the task by himself in 12 hours, and the second in 10 hours. After two hours of joint work left, the first worker went to a doctor, and the second finished the job himself. How many hours worked the second worker himself? - Together 39671
Three workers were to lay the parquet floor. If everyone worked alone, the first would finish the job in 30 hours, the second in 24 hours, and the third in 20 hours. How long will they do the floor if they work together? - Planting 27201
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f
- Forestry workers
56 laborers have employed planted trees in the forest. For 8 hour work, a day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day? - Diggers
The excavation was carried out in 4 days, and five workers worked on it for 7 hours daily. Determine how long it would take to excavate if seven workers worked on it 8 hours a day. - Workshops
The first workshop will do the robot itself in 15 days, and the second workshop in 10 days. They started together, but only the second workshop worked after three days. How many days will the work be done? - Tmp workers
Three temporary workers cleaned 60 m of the walkway in 5 hours. How many meters of the walkway were cleared by seven volunteers for eight hours? - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c
- Work
The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together. Then the first worker did the remaining work himself. In what proportion should the remuneration of the workers - Summerjob
Temporary workers Franta ties a sheaf of hay in 20 minutes, Lojza only a quarter in the same time. How many sheaves do they tie together in 8 hours? - Simultaneously 4746
One painter paints the school in 7 days, the other in 6 days. The school had to be painted in 2 days. A third painter was called in, and they all worked simultaneously. In how many days would this third painter paint the school by himself?