Part-timers

Six part-timers would take seven hours to pick strawberries. How long would this work take if two more temporary workers were added after three hours?

Correct answer:

t =  6 h

Step-by-step explanation:

6 7=6 3+(6+2) (t3)  8t=48  t=6=6 h



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Lumberjacks
    stromy Fifteen lumberjacks would take 12 days to destroy the broken trees. How many days would this work require if 5 workers added to it after 4 days?
  • Four workers
    wood Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • Temporary workers
    work Three temporary workers work in the warehouse and unload the goods in 9 hours. At what time would five temporary workers unload the same products?
  • Strawberries
    strawberries Father collects strawberries himself in 4 hours, son in 14 hours. How long will it take them along when dad comes to help his son collect strawberries after 3 hours?
  • Diggers
    workers The excavation was carried out in 4 days and 5 workers worked on it for 7 hours a day. Determine how long it would take to excavate if 7 workers worked on it 8 hours a day.
  • Diggers
    digging Eight diggers will do the job in 85 hours. After 21 hours, 3 diggers had to leave. How many hours will the work be done?
  • Digging
    digging The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?
  • Five tractors
    tractors Five tractors plow the fields in 4.8 hours. How long will it take to plow the field when, after an hour and a half of work, two tractor drivers have been called up for another task?
  • Pumps
    cerpadla Four identical pumps fill the tank in 40 hours. How many pumps would we have to use if we wanted to save 8 hours?
  • The orchard
    jablone 4 temporary workers harvested the orchard in 9 days. How many temporary workers we need for six days?
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Parquet floor
    Parkett Three workers laid parquet floor for 2.301 hour. The first one would do this work alone 7 hours, the second in 6 hours. For how many hours would fulfill this work the third worker, if he worked alone?
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta
  • Six workers
    workers Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?
  • Water inlets
    pipe Inlet valve with a flow rate of 12 liters per second is filled tank for 72 minutes. How long take to fill full tank if we open one more such valve half an hour after?
  • Tractors
    tractor Six tractors plowing the field for 8 days. After two days, two tractors broke down. How many days were prolonged work in the field?
  • Seven workers
    wood Seven workers clear the glade in 22 hours. How many workers would need to be done in 8 hours?