Four workers were supposed to build 200m of the fence in 15 days. However, after 3 days, two more workers came to their aid. All workers were equally efficient. Calculate how many meters of the fence (from the original 200m) remained after the first 3 days.
Correct answer:
Tips for related online calculators
Check out our ratio calculator.
You need to know the following knowledge to solve this word math problem:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Part-timers 6344
Certain work was to be done by 21 workers during an eight-hour workday, due in 12 days. After five days, temporary workers came to their aid. They all worked together for 7 hours a day and finished the job in 6 days. How many part-timers were there? - Bricklayers
The first bricklayer would build a wall in 3 days, the second in 4 days. The first bricklayer worked alone for a day, then the second bricklayer came to his aid and finished the work together. How long did it take to build the wall? - Agricultural 65594
Six identical harvesters were supposed to work on the harvest for 12 days in the agricultural cooperative. After three days, however, two harvesters left for another team. Find how long the harvest time in the farm cooperative has increased. - Initially 35123
Five hundred ninety pieces of clothing were to be sewn in the two branches of the tailor's workshop. However, 30% more were sewn in the first workshop and 10% more in the second. They sewed a total of 703 pieces. How many products were initially supposed
- Lecturers 6099
Three lecturers will create 75 tasks in two and a half days. In how many days will it take at least five lecturers to create enough exercises for the exercise book, which should contain 300 exercises? (we assume that all tutors are equally efficient and w - Remaining 6007
In the park, one-third of all the leaves on the trees fell on the first day. On the second day, a quarter of what remained on the branches fell, and a third of the remaining leaves on the third day. Half of the leaves were blown off the trees on the fourt - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Exhibition 18783
During 3 days, 2870 people went to the exhibition. On the second day, 140 more people came to the exhibition than on the first day. On the 3rd day, there were 1.5 times more people at the exhibition than on the second day. How many people visited the exhi - Manuscript 54691
The typist was given the task of rewriting the manuscript of the adventure book in 8 days. However, she completed the task in 6 days because she rewrote 6 more pages per day than she was supposed to rewrite. Determine the number of pages of an adventure b
- Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work. - Worker's performance
Fifteen workers paint 180 m fence in 3 days. In how many days will nine workers paint a 360 m fence? We assume that each worker has the same, constant and unchangeable performance. - Temporary 67594
Two temporary workers comb apples from 15 apple trees in 5 hours and 20 minutes. After two hours, three other temporary workers came to help them. How long did it take to comb apples from these 15 trees? - Two shops
In two different shops, the same skis had the same price. In the first, however, they first became more expensive by 20% and then cheaper by 5%. In the second, they were first cheaper by 5% and then more expensive by 30%, so after these adjustments in the - Materials 4405
Two trucks were supposed to load the building materials in 10 days. After 6 days of work, the first car broke down, and the second one carried building materials for another 9 days. How many days would the first and second cars take the building materials
- Rediscounted 29431
At the beginning of the season, roller skates became 15% more expensive. In the autumn, they were rediscounted by 15% of the new price. Their price after the price increase and discount was € 195.50. What was their original price? - Delivering 80805
The courier company delivers the ordered goods through the e-shop. If the delivery were made by 2 cars, it would be completed in 6 hours. However, after 4 hours, the first car's driver stopped delivering, and the second car continued to deliver for anothe - Workers
Ten workers must pave road street for 22 working days. After four days were for speeding up work, added two more workers. a) After how many work days now workers complete the paved road? b) How many working days does a total paved road take?