Budget plan
In the construction of the building, the planned budget exceeded 13%, which was 32,500 euros. How many euros did it cost to build the building?
Correct answer:

Tips for related online calculators
Our percentage calculator will help you quickly and easily solve a variety of common percentage-related problems.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsUnits of physical quantitiesGrade of the word problem
Related math problems and questions:
- Chocolate
Chocolate, which initially cost 1.5 euros, was increased by 40%. How many euros did it cost?
- Construction 55441
By improving the work process, constructing a family house saved CZK 111,600, which was 5% of the total budget. What was the original budget for a family house?
- Farm
Agricultural cooperative (farm) produced 14144 liters of milk for 16 days, which exceeded the plan by 1984 liters. How many liters of milk had a day planned to produce?
- One-twentieth 82239
Peter and Honzo decided to build the building as quickly as possible. They built one-twentieth of the building in ten minutes. After 20 minutes, three more friends joined. Everyone was building at the same pace. How many minutes did it take to build the s
- Highway repair
The highway repair was planned for 15 days. However, it was reduced by 30%. How many days did the repair of the highway last?
- Construction 4130
By improving the work process, constructing a family house saved CZK 111,600, which was 9% of the total budget. What was the original budget for a family house?
- Construction 81294
The first group of construction workers would build a certain section of highway in 15 weeks, and the second group would make it in 10 weeks. After four weeks of working together, the second group was dismissed, and only the first group continued to work.