Factory order completion
Factory A can fulfill the order independently in 10 days. Factory B fulfills the same order in 16 days. How many days will the order be completed if only plant B works on it for 3 days and then both plants together?
Final Answer:

Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Looking for a statistical calculator?
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
statisticsalgebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Plant order completion
Race A can fulfill the order in 12 days, and race B can fulfill the same order in 18 days. If both plants work together, how many days will the order be fulfilled? - Workshop shifts
Workshop A can fulfill a specific order in 8 changes, workshop B in 10 modifications. How many shifts will the job be completed if workshop A works on only the first two shifts and both workshops work on the remaining shifts? - Two companies
Company A can fulfill the order in 12 days, and company B can fulfill the same order in 18 days. If only company A works on the order for the first two days and then both companies work on it for the remaining days, how many days will the order be fulfill - Workshop order completion
The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete - The factory
The factory z can complete an order in 12 days, and factory p can complete it in 18 days. How many days does an order complete when the first two days work only the factory z and then both factories? - On the bed
We want to plant several rows of cauliflower seedlings and several rows of lettuce seedlings alternately on the bed. The cauliflower seedlings are planted 45 cm apart, the lettuce seedlings 25 cm apart. Planting seedlings of both types of plants starts fr - Jewelry factory
In a jewelry factory, three assemblers make beaded necklaces. Marcus can make 22 necklaces per hour all day long. Anita can make 25 necklaces for her first three hours of the day and then slow down to 16 necklaces for the rest of the day. Yara can make 27