The factory
The factory z can complete an order in 12 days, factory p in 18 days. How many days does an order completed when the first two days work only the factory z and then both factories?
Correct answer:
Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Looking for a statistical calculator?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Independently 12921
Factory A can fulfill the order independently in 10 days. Factory B fulfills the same order in 16 days. How many days will the order be completed if only plant B works on it for 3 days and then both plants together? - Two companies
Company A can fulfill the order in 12 days, and company B the same order in 18 days. How many days will the order be fulfilled if only company A works on it for the first two days, then the remaining days for both companies? - Modifications 3317
Workshop A can fulfill a specific order in 8 changes, workshop B in 10 modifications. How many shifts will the job be completed if workshop A works on only the first two shifts and both workshops work on the remaining shifts? - Fulfilled 29001
Race A can fulfill the order in 12 days, and race B the same order in 18 days. How many days will the order be fulfilled if both plants work together?
- Mukls
The six workers' working group would order jobs completed within 21 working days. How many workers must be added to complete a contract in 14 working days? - Efficiently 65484
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Three workshops
One workshop can complete the task in 48 days, the second in 30 days, and the third in 20 days. In how many days would the task be completed if all workshops worked?