Carpenters 44401
Eight carpenters will make 30 chairs in 2 days. In how many days will ten carpenters make 72 chairs?
Correct answer:

Tips for related online calculators
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
basic operations and conceptsUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Carpenters
Carpenters 1 and 2 spend ten days and five days, respectively, to make one table. The first carpenter and 30 made 50 tables by the second. What is the average time spent on the products?
- Together
Grandfather, father, and son are carpenters. They decided to make a wardrobe. Father produces it for 12 hours, his son for 15 hours, and grandfather for 10 hours. How long will they make it together?
- Salami
We have six kinds of salami, six of which have ten pieces, and one of which has four pieces. How many ways can we distinctly choose five pieces of salami?
- Exhibition 4753
The carpenter has to attach slats for hanging paintings on the exhibition hall wall, which has a length of 39 m and 40 cm. The length of one bar is 2 m. Will 22 laths be enough for carpenters?
- Custom-made 81913
On October 1, 2022, the customer ordered a custom-made kitchen from a carpentry company. Delivery time is 1 month. Four carpenters should work on the order in the workshop for 21 working days. Will they be able to deliver the kitchen on time if one of the
- Identical 44271
Ten identical trucks will take 240 tons of concrete to build the dam in 3 working days. How many tons of concrete will seven trucks take to make the dam in 5 days?
- Manday, manhour
Job problem: 10 men can make 20 toys in 12 days working 12 hours a day.Then, in how many days can 24 persons make 32 toys working 16 hours a day?