Production 24021

The plant has to complete the order in 40 working days. Production takes place in two workshops. In the first one, there are more workers; therefore, they would complete the order themselves in 70 working days. In the second workshop, they would complete the order in 90 days.
a) Will the order be completed on time?
b) What day will it be?

Correct answer:

t =  39.375

Step-by-step explanation:

t (1/70+1/90)=1  16t=630  t=16630=39.375  t=8315=39.375  t<40  t=39.375



Did you find an error or inaccuracy? Feel free to write us. Thank you!







Tips for related online calculators
Looking for calculator of harmonic mean?
Looking for a statistical calculator?
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions: