Workers

Group of workers washing half of the windows of the building in two hours. How long will take half the workers wash all the windows of the building?

Correct answer:

t =  8 h

Step-by-step explanation:

t=2 2 2=8 h



We will be pleased if You send us any improvements to this math problem. Thank you!






avatar




Tips to related online calculators
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Madams
    womans During the spring cleaning ladies going to wash windows. Mother takes wash all the windows 5 hours, the grandmother 3 times longer and Paula wash all windows in 2 hours. How many hours will spend washing the windows this "women's team" if working together
  • Workers 9
    okno2 If two workers fix two windows in an hour how many windows can 18 workers fix in the same two windows?
  • Seven workers
    wood Seven workers clear the glade in 22 hours. How many workers would need to be done in 8 hours?
  • Two workers
    2workers Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker next half of the work it will take 25 hours. How long would it take job them separately?
  • Two workers
    mame_nizke_mzdy The first worker completed the task by himself in 9 hours, the second in 15 hours. After two hours of joint work left first worker to a doctor and the second finished the job himself. How many hours worked second worker himself?
  • The work
    clock-night-schr The work was to be done by 150 workers. At the beginning of their work, their number reduced by 40, which increased the time of work by 5 and 1/3 of the schedule. How long did work take?
  • Workers
    work 9 workers dig a canal 120 meters long for eight hours. For how long would be dig five workers canal 200 meters long?
  • Workers
    calc Four workers plan to work on the gym floor for six hours. After an hour of working together, one of the workers went to the doctor. How long will it take the remaining three workers to finish the job?
  • Work
    workers The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together, then the first worker did the remaining work himself. In what proportion should the remuneration of the workers
  • Four workers
    wood Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • Workers 2
    delnik Worker dug the trench for 7 hours, another worker for 10 hours. They recruited to work even one worker more. Digging should be done for 2 hours. For how long would dig third worker alone?
  • Two workers
    work One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the second was recalled, and the first completed the job itself in 5 hours. How many hours did they work together, and how much did
  • Six workers
    workers Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?
  • Temporary workers
    work Three temporary workers work in the warehouse and unload the goods in 9 hours. In what time would five temporary workers unload the same products?
  • Mukls
    Chinese women workers The working group, in which 6 workers would ordered job completed within 21 working days. How many workers must be accept yet that the contract will be completed in 14 working days?
  • Diggers
    workers The excavation was carried out in 4 days and 5 workers worked on it for 7 hours a day. Determine how long it would take to excavate if 7 workers worked on it 8 hours a day.
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta